Miscellaneous action | | | 1/14/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 4/28/2010 | 4/29/2010 | 4/29/2010 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 4/26/2010 | 4/27/2010 | 4/27/2010 | P | DONE |
Troy Cobbley
|
|
|
Mike B is the contact. Thanks Inspection requested from web by: Stan Beus Phone #: ###-####
There were no approved plan on the job site. There was missing escutcheon and two sprinklers were blocked by exposed duct work.
|
INSP-Sprinkler Rough-in | 3/11/2010 | 3/11/2010 | 3/11/2010 | P | PASS |
Troy Cobbley
|
|
|
The piping changes have been addressed by tim frost and per mike a lintel is being installed to separate the shower from the restroom. Sprinkler piping can be covered.
|
Miscellaneous action | | | 3/10/2010 | | DONE |
|
|
|
New proof hydraulics were submitted due to construction changes. The hydraulics are ok.
|
INSP-Sprinkler Rough-in | 3/8/2010 | 3/9/2010 | 3/9/2010 | P | FAIL |
Troy Cobbley
|
|
|
Resubmittals are required due to pipe routing and sizing that differs from the approved plans. One pendant on the second floor needs to be relocated since it exceeds 8' from the kitchen wall. There is shadowing in the second floor bathroom. An additional head will be required or a lintel/soffit installed as discussed.
|
CHANGE STATUS TO (ISS) | | | 1/7/2010 | | DONE |
|
|
|
picked up plan mod
|
(F) Reprint permit | | | 1/7/2010 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 12/21/2009 | | 12/23/2009 | | DONE |
Tim Frost
|
|
|
12/23/2009 15:13:00 TRF - activity updated through activity FIRA22 from case FIR09-00681.
|
Sprinkler Plan Check | 12/23/2009 | | 12/23/2009 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/23/2009 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 12/23/2009 | | DONE |
|
|
|
t/c w cameron at ###-#### - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 12/23/2009 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/21/2009 | | |
Tisha Gallop
|
|
|
Plan modification: Received application and three copies of submittal documents and plan sheet FP1; taken to Fire Review
|
Issue and Print Permit | | | 12/14/2009 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 12/1/2009 | | 12/11/2009 | | DONE |
Tim Frost
|
|
|
12/11/2009 15:59:35 TRF - activity updated through activity FIRA22 from case FIR09-00681.
|
Plan assigned to (Tim) | 12/10/2009 | | 12/11/2009 | | DONE |
Tim Frost
|
|
|
12/11/2009 15:59:35 TRF - activity updated through activity FIRA22 from case FIR09-00681.
|
Sprinkler Plan Check | 12/11/2009 | | 12/11/2009 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/11/2009 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 12/11/2009 | | 12/11/2009 | | DONE |
|
|
|
|
Telephone call | | | 12/11/2009 | | DONE |
|
|
|
t/c w cameron at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 12/11/2009 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/10/2009 | | |
Tisha Gallop
|
|
|
received application and three copies of submittal documents and plan sheets FP1; taken to Fire Review
|
Sprinkler Plan Check | 12/4/2009 | | 12/4/2009 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are annotations on the plans.
|
1st review completed | | | 12/4/2009 | | FAIL |
Tim Frost
|
|
|
|
Telephone call | | | 12/4/2009 | | DONE |
|
|
|
left vm for cameron at ###-#### - permit denied - needs to be picked up and resubmitted
|
Application received | | | 12/1/2009 | | |
|
|
|
|
Pending Assignment by SAM | 12/1/2009 | | 12/1/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
12/1/2009 16:46:48 ALR - activity updated through activity FIRA158 from case FIR09-00681.
|