Miscellaneous action | | | 1/14/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 7/22/2010 | 7/26/2010 | 7/26/2010 | A | PASS |
Troy Cobbley
|
|
|
The forward flush passed. Permit for Phase I passed.
|
INSP-Final Inspection | 5/25/2010 | 5/26/2010 | 5/26/2010 | A | FAIL |
Troy Cobbley
|
|
|
The alarm interconnection for the devices located in phase I were tested today. It appears the only outstanding item for phase I is the forward flush failed.
|
INSP-Sprinkler Rough-in | 5/20/2010 | 5/21/2010 | 5/21/2010 | A | PART |
Forrest France
|
|
|
Walkthrough of phase one completed, noted one head at the kitchen area out of adjustment, missing escutcheon at one dry pendent north side entry, one room at the first floor is missing a ceiling at this time. Remainder of inspection passed, final pending fire alarm testing for riser supervision.
|
INSP-Sprinkler Rough-in | 5/14/2010 | 5/14/2010 | 5/14/2010 | P | PASS |
Troy Cobbley
|
|
|
The fire sprinklers are complete in the pool/shower area.
|
INSP-Sprinkler Rough-in | 5/5/2010 | 5/5/2010 | 5/5/2010 | P | PASS |
Troy Cobbley
|
|
|
The pendants/piping in the corridor at the pool area is ok for cover.
|
INSP-Sprinkler Rough-in/Hydro | 5/4/2010 | 5/4/2010 | 5/4/2010 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro test for all of the new sprinkler piping passed. Also see the city approved plans for additional areas where sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 3/31/2010 | 4/1/2010 | 4/1/2010 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler rough-in and the hydro test for the basement area. This includes the anti-freeze loop.
|
INSP-Sprinkler Rough-in | 3/26/2010 | 3/26/2010 | 3/26/2010 | P | PASS |
Troy Cobbley
|
|
|
see the city approved plans for piping the is ok for cover.
|
INSP-Sprinkler Rough-in | 3/18/2010 | 3/19/2010 | 3/19/2010 | A | PART |
Forrest France
|
|
|
Pendent head at the locker room vestibule hard lid ceiling is okay for cover- see clouded area with today's date and initials on approved plan set sheet FP-4.
|
INSP-Sprinkler Rough-in | 3/16/2010 | 3/17/2010 | 3/17/2010 | A | PART |
Forrest France
|
|
|
See stamped plan set sheet FP-4 for clouded area initialed and marked with today's date for locations of overhead work at sheetrock ceilings okayed for cover. Missing coverage at one adjacent vestibule to be verified prior to cover and not included in this inspection.
|
INSP-Sprinkler Rough-in/Hydro | 3/10/2010 | 3/10/2010 | 3/10/2010 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro tests of the new west end wet system piping and the anti-freeze system/south canopy passed. The combustible concealed pockets on the previous correction notice have been provided with sprinkler coverage and can be covered as marked ok on the city approved plans.
|
INSP-Sprinkler Rough-in | 3/2/2010 | 3/3/2010 | 3/3/2010 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where rough-in inspection passed and other areas marked "ok" where piping can be covered. I noted atleast two locations where a combustible concealed area existing that has no sprinkler protection and a location where a pendant head symbol is used on the plans but is not included in the head symbol legend. John is following up with the design department.
|
INSP-Sprinkler Rough-in | 3/2/2010 | 3/2/2010 | 3/2/2010 | P | CANC |
Troy Cobbley
|
|
|
John was not quite ready for inspection when I was available so we've rescheduled for first thing tomorrow morning.
|
INSP-Sprinkler Rough-in | 2/25/2010 | 2/25/2010 | 2/25/2010 | P | PART |
Forrest France
|
|
|
Antifreeze system piping at the west canopy as marked on approved plan set with todays date and initialed okay for cover, one minor adjustment made while on sie, also okayed insulation fill at perimeter soffits on the new porte cochere.
|
INSP-Sprinkler Rough-in | 2/22/2010 | 2/22/2010 | 2/22/2010 | P | PASS |
Troy Cobbley
|
|
|
The modified underground supply piping is ok to cover. The old supply line has been capped off and abandoned.
|
INSP-Sprinkler Rough-in | 2/18/2010 | 2/19/2010 | 2/19/2010 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where the sprinkler piping can be covered. They have been marked in red.
|
INSP-Sprinkler Rough-in | 2/18/2010 | 2/18/2010 | 2/18/2010 | P | CANC |
Troy Cobbley
|
|
|
Cancelled due to time constraints. Rescheduled with John Phone #: ###-#### for tomorrow morning.
|
INSP-Sprinkler Rough-in | 2/8/2010 | 2/9/2010 | 2/9/2010 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where the sprinkler piping can be covered.
|
Plan resubmittals received | | | 2/4/2010 | | |
Tim Frost
|
|
|
rec'd 3 sets
|
Plan assigned to (Tim) | 2/4/2010 | | 2/4/2010 | | DONE |
Tim Frost
|
|
|
2/4/2010 10:49:43 TRF - activity updated through activity FIRA22 from case FIR09-00707.
|
Sprinkler Plan Check | 2/4/2010 | | 2/4/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 2/4/2010 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/4/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 2/4/2010 | | 2/4/2010 | | DONE |
|
|
|
|
Telephone call | | | 2/4/2010 | | DONE |
|
|
|
t/c w chris wilson at ###-#### - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 2/4/2010 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/4/2010 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 1/28/2010 | 1/28/2010 | 1/28/2010 | P | PART |
Troy Cobbley
|
|
|
See the city approved plans for locations marked "ok" in red where piping can be covered. Part of todays inspection included the new system at the west end of the building. Here I found at least two additional sprinkler heads added in the remote area and per the plans the pendant heads in the attic area are mounted on the branchlines. As installed there are two 90 elbows and 1" piping between the branchline and the pendant heads. This occurs in the remote area. I spoke to John on site and Jeff in Treasure Valley Fires office about the need for resubmittals or at the very least contacting Tim Frost with plan review.
|
INSP-Sprinkler Rough-in | 1/25/2010 | 1/25/2010 | 1/25/2010 | P | CANC |
Troy Cobbley
|
|
|
Cancel this inspection per Jeremy since work was not complete. Plans were just issued today but an early start agreement was issued on 12-28-2009.
|
Issue and Print Permit | | | 1/25/2010 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/22/2010 | | 1/22/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/22/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 1/22/2010 | | 1/22/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 1/22/2010 | | DONE |
|
|
|
t/c w jeff packham at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 1/22/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 1/21/2010 | | |
Tim Frost
|
|
|
rec'd 3 sets of plans
|
Miscellaneous action | | | 1/20/2010 | | DONE |
Tim Frost
|
|
|
Emailed comments to Chris
|
Sprinkler Plan Check | 1/20/2010 | | 1/20/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
Telephone call | | | 1/20/2010 | | DONE |
|
|
|
t/c w chris at ###-#### - permit denied - needs to be picked up and resubmitted
|
Plan resubmittals received | | | 1/19/2010 | | |
Tim Frost
|
|
|
rec'd 3 sets of plans
|
Telephone call | | | 12/18/2009 | | DONE |
|
|
|
t/c w chris at ###-#### - permit denied - needs to be picked up and resubmitted
|
Plan assigned to (Tim) | 12/15/2009 | | 12/17/2009 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/17/2009 | | 12/17/2009 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 12/17/2009 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 12/17/2009 | | DONE |
Tim Frost
|
|
|
Emailed review to Chris
|
Application received | | | 12/15/2009 | | |
|
|
|
|
Pending Assignment by SAM | 12/15/2009 | | 12/15/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
12/15/2009 11:16:04 ALR - activity updated through activity FIRA158 from case FIR09-00707.
|