Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR09-00708
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 350 S ALLUMBAUGH WAY
Project NameGrace @ Englefield Green
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of five systems (3 dry systems and 2 wet systems). A new 6" UDG supply was brought in under permit FIR09-00581. The dry systems utilize a combination of special application attic sprinklers and standard sprinklers. The wet systems utilize CPVC piping and quick response sprinklers. There are two separate riser locations. The second riser location is supply by a 6" bulk main from the main riser.

(Grace @ Englefield Green - Assisted Living) Scope of work includes construction of a 66,772 sq. ft., single story, fully sprinklered, Type VA construction, divided by (4) 2-hour fire walls to create three buildings for allowable floor area compliance based on type of construction (11, 857 sq. ft. / 43,167 sq. ft. / 11,698 sq. ft.); with 85 supervised residential units (34 one bedroom units @ 528 sq. ft.; 37 Studio Units @ 388 sq. ft.; 2 two bedroom units @ 816 sq. ft.; 2 two bedroom units @ 780 sq. ft. and 4 Friendship Units @ 366 sq. ft.); use of 2-hour fire walls and (4) 1-hour smoke barrier walls create (5) smoke compartments; 1-hour smoke partitions to create a smoke resistant corridor system; a kitchen, dining and socializing area; laundry, mechanical and common use support areas. There are four interior courts (3,536 sq. ft. / 2,911 sq. ft. / 4,492 sq. ft. / 3,536 sq. ft.) that exit back through the facility; installation of electrical, mechanical, plumbing, sprinkler and alarm systems; and all associated site work and landscaping, all per reviewed plans to include red-line review notes and all attached plan review conditions / comments as part of the reviewed plans. Carports ARE NOT a part of this permit. They will require separate submittals. Drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  1/14/2011 DONE
Sent to records for scanning.
INSP-Final Inspection6/1/20106/2/20106/2/2010APASS
DetailsTroy Cobbley
Permit finaled. Accelerators have been installed and the two low air signals were received.
INSP-Sprinkler Rough-in6/1/20106/1/20106/1/2010PPASS
DetailsTroy Cobbley
Forward flush passed.
INSP-Final Inspection5/27/20105/28/20105/28/2010AFAIL
DetailsTroy Cobbley
The north and south dry pipe systems need accellerators per NFPA 13 - 7.2.3.3 since they exceed 500 gallons. The central system does have the accellerator but did not meet the 60 second rule as per NFPA 13- 7.2.3.2 since it has 755 gallons. Also see table 7.2.3.6.1. Still need to verify low air signal to the facp for the north system and the central system. A zone map is need showing the areas covered by each sprinkler system and the location of the control valves. All signals other than the two low air signals were sent and received at the fire alarm panel.
INSP-Final Inspection5/19/20105/19/20105/20/2010PFAIL
DetailsTroy Cobbley
Todays inspection was for the two north most corridors and the residence rooms associated with them. All items were ok except quite a few canopies are falling off of the pendant heads. Lonnie said he would address the issue.
INSP-Sprinkler Rough-in/Hydro4/22/20104/22/20104/22/2010PPASS
DetailsTroy Cobbley
The insulation has been replaced over the wet sprinkler piping in the south end of the building. The blow in insulation is ok to be installed.
INSP-Sprinkler Rough-in3/29/20103/29/20103/29/2010PPASS
DetailsTroy Cobbley
The riser room and the adjacent electrical room are ok to cover.
INSP-Sprinkler Rough-in3/24/20103/25/20103/25/2010PPASS
DetailsTroy Cobbley
The three rooms near the nurses station are now ok to cover.
INSP-Sprinkler Rough-in3/24/20103/24/20103/24/2010PFAIL
DetailsTroy Cobbley
The tenting issues at the nurses station area have not been addressed. I spoke to Herb about what is needed to get a cover approval in this area.
INSP-Sprinkler Rough-in3/22/20103/23/20103/24/2010PPART
DetailsTroy Cobbley
The insulation blocking sprinkler coverage in the soffits has been addressed. All other areas in the lounge/hall areas, as discussed, can be covered. Three small rooms in the nurses station area can not be covered due to sprinkler pipe tenting issues.
INSP-Sprinkler Rough-in3/17/20103/17/20103/18/2010PPART
DetailsForrest France
See annotations initialed with today's date on sheet FP-4 including the library, private dining, activity, and TV lounge rooms okayed for ceiling cover. NOTE: Soffits at the adjacent hallway and library/dining rooms are not yet approved for cover due to batt insulation blocking attic sprinkler coverage in these combustible pockets- Discussed solutions with contractor on site.
INSP-Sprinkler Rough-in3/16/20103/17/20103/17/2010ACANC
DetailsTroy Cobbley
Per telephone discussion with Lonnie this will be rescheduled for when the insulation is finished.
INSP-Sprinkler Rough-in3/10/20103/11/20103/11/2010APASS
DetailsTroy Cobbley
See the city approved plans for new locations where the sprinkler piping can be covered. Lonnie and I found the the south third of the building sprinkler piping covered without my cover inspections. I agreed for this one occation that instead of removing ceilings that I would access the piping in the attic as long as the insulation has been removed for inspection and then schedule a second inspection for the re-installation of the insulation.
INSP-Sprinkler Rough-in/Hydro2/23/20102/24/20102/24/2010PPASS
DetailsTroy Cobbley
The 24 hour air test on the last dry system passed.
INSP-Sprinkler Rough-in2/23/20102/23/20102/23/2010PPART
DetailsForrest France
Begin 24 hour air test at the 4" dry valve at 3:30PM @48 psig.
INSP-Sprinkler Rough-in/Hydro2/22/20102/22/20102/22/2010PPASS
DetailsTroy Cobbley
The overhead hydro tests of the last wet and dry system on the south end of the building passed.
INSP-Sprinkler Rough-in/Hydro2/18/20102/19/20102/19/2010AFAIL
DetailsTroy Cobbley
The last dry and wet system overhead hydro tests failed again. Will need to try again.
INSP-Sprinkler Rough-in2/17/20102/18/20102/18/2010APASS
DetailsTroy Cobbley
See the city approved plans marked with todays date for partial rough-in inspections on the last wet and dry systems.
INSP-Sprinkler Rough-in/Hydro2/17/20102/18/20102/18/2010AFAIL
DetailsTroy Cobbley
The last wet and dry system overhead hydro tests failed. There was visable leakage on the dry system.
INSP-Sprinkler Rough-in2/11/20102/12/20102/12/2010APASS
DetailsTroy Cobbley
See the city approverd plans for locations with todays date for piping inspected. I The inspection included both wet and dry systems.
INSP-Sprinkler Rough-in/Hydro2/10/20102/11/20102/11/2010APASS
DetailsTroy Cobbley
The overhead hydro test of dry systems 3 and 4 and wet system 1 passed.
INSP-Sprinkler Rough-in2/10/20102/10/20102/10/2010PPASS
DetailsTroy Cobbley
The 24 hour air test on system 4 passed.
INSP-Sprinkler Rough-in2/8/20102/9/20102/10/2010PPASS
DetailsTroy Cobbley
The rough-in inspection for system 4 attic piping passed. Three baffles need installed as discussed. The 24 hour air test for system 4 was started at 2:00 with 52psi on the guage.
INSP-Sprinkler Rough-in1/28/20101/28/20101/28/2010PPASS
DetailsTroy Cobbley
See the city approved plans for piping locations with todays date where sprinkler piping can be covered.
INSP-Conference1/22/20101/25/20101/25/2010ADONE
DetailsTroy Cobbley
Sprinkler pendant locations in relationship to pendant lights came into question. Per NFPA 13 and discussion with Tim Frost, the pendant lights will not be an issue.
INSP-Sprinkler Rough-in1/21/20101/22/20101/22/2010APASS
DetailsTroy Cobbley
24 hour air test on dry system #3 passed. See the city approved plans where part of the sprinkler piping for wet system #1 can be covered.
INSP-Sprinkler Rough-in1/20/20101/21/20101/21/2010PPART
DetailsTroy Cobbley
The 24 hour air test was started at 11:00 with 44psi on the guage.
Telephone call  1/19/2010 DONE
DetailsTim Frost
Per phone call with Jim at TREASURE VALLEY FIRE PROTECTION the sprinklers in hallway 4 shown on FP8 will be changed from B-B to standard sprinklers due to structural modifications. The changes will be shown on as built drawings. This was approved by TRF
INSP-Sprinkler Rough-in1/14/20101/15/20101/15/2010APART
DetailsTroy Cobbley
Todays inspection was for the dry system #3. The rough-in is passed in general. The problems needing corrected include restraints are missing on the three branchlines over the kitchen area, through bolts are required for all of the earthquake connections to the wood members, the laterals and longitudinals can not be connected together unless calc'ed that way and 3/4" through bolts are required not the 3/8" as installed.
Inspection Record Card- Fire12/30/2009 12/30/2009 DONE
DetailsPatricia Smith
Telephone call  12/30/2009 DONE
Details
t/c w jim darr at ###-#### - permit ready and fees given
Permit Ready to Issue  12/30/2009 DONE
Details
Issue and Print Permit  12/30/2009 DONE
Plan assigned to (Tim)12/15/2009 12/29/2009 DONE
DetailsTim Frost
12/29/2009 17:01:00 TRF - activity updated through activity FIRA22 from case FIR09-00708.
Sprinkler Plan Check12/29/2009 12/29/2009 PASS
DetailsTim Frost
Please, see attached comments.
There are annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  12/29/2009 DONE
DetailsTim Frost
Plan resubmittals received  12/24/2009  
DetailsTim Frost
rec'd 3 sets
Sprinkler Plan Check12/21/2009 12/21/2009 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  12/21/2009 DONE
DetailsTim Frost
Miscellaneous action  12/21/2009 DONE
DetailsTim Frost
Emailed comments
Telephone call  12/21/2009 DONE
Details
t/c w jim darr at ###-#### - permit denied - needs to be picked up and resubmitted
Application received  12/15/2009  
Pending Assignment by SAM12/15/2009 12/15/2009 DONE
DetailsAlexandra L. DeYoung
12/15/2009 11:19:24 ALR - activity updated through activity FIRA158 from case FIR09-00708.