Miscellaneous action | | | 6/7/2010 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 5/28/2010 | 6/1/2010 | 6/1/2010 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Remaining deficiencies corrected.
|
INSP-Alarm Testing | 5/28/2010 | 5/28/2010 | 5/28/2010 | P | DONE |
Troy Cobbley
|
|
|
Relocate the a/v in the dining area, provide an additional strobe in the lobby and provide an additional strobe in the courtyard corridor as discussed and then test. Still need to verify operation of the remaining smoke dampers. Need map for facp and signal report
|
INSP-Alarm Testing | 5/26/2010 | 5/27/2010 | 5/27/2010 | A | DONE |
Troy Cobbley
|
|
|
See the city approved plans for the initiating devices theat are marked with OK thant have been tested. This included phone line troubles, verification of separate phone lines, duct smoke detectors, pull stations, smoke detectore and heat detectors. Items left to test include the fire sprinkler interconnections, smoke dampers, supervision of the NAC panels, EOL voltage verifications and verifications of a/v sync.. As-builts are also required reflecting actual locations of devices and devices that have been deleted.
|
INSP-Alarm Testing | 5/24/2010 | 5/25/2010 | 5/25/2010 | A | CANC |
Troy Cobbley
|
|
|
Per Matt the fire alarm system is not ready for inspection and will need to be rescheduled.
|
INSP-Conference | 3/12/2010 | 3/12/2010 | 3/12/2010 | P | DONE |
Troy Cobbley
|
|
|
I spoke to Matt about duct smoke detector placement and possible manometer testing to verify correct function of the detectors.
|
INSP-Conference | 1/19/2010 | 1/20/2010 | 1/20/2010 | A | DONE |
Troy Cobbley
|
|
|
The stop work order that had been previously posted for the fire alarm installation is being lifted due to the fire alarm plans being issued.
|
Inspection Record Card- Fire | 1/19/2010 | | 1/19/2010 | | DONE |
|
|
|
|
Telephone call | | | 1/19/2010 | | DONE |
|
|
|
t/c w matt at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 1/19/2010 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/19/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (Stephanie) | 12/15/2009 | | 1/15/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
1/15/2010 16:04:25 SLC - activity updated through activity FIRA24 from case FIR09-00711.
|
Alarm Plan Check | 1/15/2010 | | 1/15/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
see review comments and redlined plans
|
PLANS TAKEN FRONT DESK ALARM | | | 1/15/2010 | | DONE |
|
|
|
approved redlined plans available at front counter
|
Plan resubmittals received | | | 1/12/2010 | | |
Stephanie L. Cobbley
|
|
|
rec'd 3 sets of plans
|
Miscellaneous action | | | 1/6/2010 | | DONE |
|
|
|
A Stop work order has been issued due to fire alarm devices and wiring being installed without an approved permit. Work order is for further installation of fire alarm and installation of sheetrock that will cover wiring and/or backboxes. I gave the job superintendent permission to insulate the exterior walls.
|
1st review completed | | | 12/18/2009 | | DONE |
|
|
|
|
Alarm Plan Check | 12/18/2009 | | 12/18/2009 | | FAIL |
Stephanie L. Cobbley
|
|
|
See review comments and red lines
|
Telephone call | | | 12/18/2009 | | DONE |
|
|
|
Spoke to Matt Casey to let him know that plans would be denied and why.
|
Miscellaneous action | | | 12/18/2009 | | DONE |
|
|
|
Faxed review comments for failed drawings to Matt Casey
|
Miscellaneous action | | | 12/18/2009 | | DONE |
|
|
|
Placed failed, redlined plans and review comments in the drawer at the front desk.
|
Miscellaneous action | | | 12/18/2009 | | DONE |
Tisha Gallop
|
|
|
contractor picked up denied plans
|
Application received | | | 12/15/2009 | | |
|
|
|
|