Miscellaneous action | | | 1/6/2010 | | DONE |
|
|
|
Fire alarm plans taken to records for scanning.
|
INSP-Final Inspection | 1/4/2010 | 1/4/2010 | 1/4/2010 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. The netcon rating was verified at 5 and all signals have been reverified.
|
INSP-Final Inspection | 12/24/2009 | 12/24/2009 | 12/24/2009 | P | NR |
Forrest France
|
|
|
Not ready for final per phone call from contractor.
|
Miscellaneous action | | | 12/24/2009 | | DONE |
|
|
|
Spoke to Shayla at Peak Alarm to let her know I would be on site between 12:15-12:30 to do the inspection. I also asked her to relay to the technician that I would need to re-verify signals in addition to verifying the Netcon rating. She indicated the technician would be notified.
|
INSP-Alarm Testing | 12/22/2009 | 12/23/2009 | 12/23/2009 | P | FAIL |
Stephanie L. Cobbley
|
|
|
(3:30pm 2nd inspection) Fire Alarm (NetCon) test failed. Rating reported a connectivity rating of 6. Minimum rating required per the manufacturers published installation instructions require a rating of 5 or less.
(11:30am 1st inspection) Fire Alarm inspection performed. At the time of this fire alarm inspection the building fire sprinkler system monitoring was verified by the central alarm monitoring facility. However, the Network Connectivity (NetCon) rating for the new AES transmitter component could not be verified by the field inspector because the applicant did not have in their possession the required tool to perform this test. The applicant agreed to return later in the afternoon, with the required tool, in order to perform the required (NetCon) test with the City field inspector. Final approval of this fire alarm permit is subject to satisfactory field inspection by the PDS/Fire inspector.
|
Plan assigned to (Stephanie) | 12/16/2009 | | 12/22/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
12/22/2009 12:04:28 SLC - activity updated through activity FIRA24 from case FIR09-00718.
|
Alarm Plan Check | 12/22/2009 | | 12/22/2009 | | PASS |
Stephanie L. Cobbley
|
|
|
see redlines and review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 12/22/2009 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Inspection Record Card- Fire | 12/22/2009 | | 12/22/2009 | | DONE |
|
|
|
|
Telephone call | | | 12/22/2009 | | DONE |
|
|
|
left message w rodney for mike at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 12/22/2009 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/22/2009 | | DONE |
|
|
|
|
1st review completed | | | 12/18/2009 | | DONE |
|
|
|
|
Alarm Plan Check | 12/18/2009 | | 12/18/2009 | | FAIL |
Stephanie L. Cobbley
|
|
|
the plans are denied because the AES is shown to be used as the FACP which is against code requirements and is not allowed.
|
Telephone call | | | 12/18/2009 | | DONE |
|
|
|
left a message for Mary Froemke and spoke to Mike at Peak Alarm letting them know the plans are denied because the AES is shown to be used as the FACP which is against code requirements and is not allowed.
|
Miscellaneous action | | | 12/18/2009 | | DONE |
|
|
|
Faxed a statement to Mike at Peak Alarm with the reasons listed for why the plans failed.
|
Plan resubmittals received | | | 12/18/2009 | | |
Tisha Gallop
|
|
|
received two copies of application, folder of submittal info and plan sheet FA00; taken to fire review
|
Application received | | | 12/16/2009 | | |
|
|
|
|