Miscellaneous action | | | 6/15/2011 | | DONE |
|
|
|
Drawings taken to records for scanning.
|
INSP-Final Inspection | 3/11/2011 | 3/11/2011 | 3/15/2011 | P | PASS |
Forrest France
|
|
|
Fire alarm permit finaled.
|
INSP-Alarm Testing | 3/10/2011 | 3/10/2011 | 3/15/2011 | P | PART |
Forrest France
|
|
|
Acceptance testing continued with corrections noted.
|
INSP-Alarm Testing | 3/11/2011 | 3/11/2011 | 3/15/2011 | A | PART |
Forrest France
|
|
|
Acceptance testing continued- see plans for annotations pertaining. Corrections underway.
|
INSP-Alarm Testing | 3/3/2011 | 3/3/2011 | 3/4/2011 | A | PART |
Forrest France
|
|
|
Dan phone #: ###-####
|
INSP-Final Inspection | 2/18/2011 | 3/2/2011 | 3/2/2011 | A | PART |
Forrest France
|
|
|
Tested fire alarm notification and initiating devices on the 2nd -7th floor tower levels, verified previous correction items are finished, booster 2 nac 3 first floor is not functional, add TS at the antifreeze loop to the points map, adjust cd and spacing at area D 2nd and 3rd floors as noted.
|
INSP-Conference | 3/1/2011 | 3/1/2011 | 3/1/2011 | P | DONE |
Forrest France
|
|
|
|
FIR-Aging Inspection | 1/10/2011 | 1/10/2011 | 1/10/2011 | | DONE |
Forrest France
|
|
|
Corrections underway.
|
INSP-Conference | 11/8/2010 | 11/8/2010 | 11/8/2010 | A | DONE |
Forrest France
|
|
|
Regarding fire alarm work in progress.
|
INSP-Conference | 10/19/2010 | 10/19/2010 | 10/20/2010 | A | DONE |
Forrest France
|
|
|
Regarding work in progress and schedule for next site visit and reinspection.
|
INSP-Alarm Testing | 8/26/2010 | 9/7/2010 | 9/15/2010 | P | FAIL |
Forrest France
|
|
|
Noted several items on initial walkthough in need of amendment- ref. plans and review notes for conditions and locations. Note: exisitng yard PIV must be provided with electronic tamper supervision.
|
INSP-Conference | 8/31/2010 | 8/31/2010 | 9/1/2010 | P | DONE |
Forrest France
|
|
|
Regarding site inspection schedule for acceptance testing.
|
INSP-Alarm Testing | 7/14/2010 | 8/6/2010 | 8/6/2010 | A | CANC |
Forrest France
|
|
|
Dan ###-####
|
FIR-Aging Inspection | 7/14/2010 | 7/14/2010 | 7/15/2010 | | DONE |
Forrest France
|
|
|
Site work in progress.
|
Issue and Print Permit | | | 4/14/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/9/2010 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/9/2010 | | 4/9/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 4/9/2010 | | DONE |
|
|
|
t/c w dan at ###-#### - permit ready and fees given
|
Alarm Plan Check | 4/8/2010 | | 4/8/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
see redlines and review comments
|
Plan assigned to (Stephanie) | 4/2/2010 | | 4/8/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
4/8/2010 15:53:08 SLC - activity updated through activity FIRA24 from case FIR10-00006.
|
PLANS TAKEN FRONT DESK ALARM | | | 4/8/2010 | | DONE |
|
|
|
approved redlined plans available at front counter
|
Plan assigned to (Stephanie) | 1/8/2010 | | 4/8/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
4/8/2010 15:50:03 SLC - activity updated through activity FIRA24 from case FIR10-00006.
|
Telephone call | | | 4/7/2010 | | DONE |
|
|
|
Spoke to Dan Hockett of State Fire and let him know that I need him to email me the battery calculations for the FACP and a bill of materials. There were many data sheets provided that do not pertain to this project, so a parts list of some sort is required to decipher what is relevant. He indicated he would be emailing me all the information by tomorrow.
|
Plan resubmittals received | | | 4/2/2010 | | |
Stephanie L. Cobbley
|
|
|
rec'd 2 sets
|
Miscellaneous action | | | 3/11/2010 | | DONE |
Tisha Gallop
|
|
|
picked up denied plans
|
Miscellaneous action | | | 3/10/2010 | | DONE |
|
|
|
I went to the job site due to questions on the 1st floor plans layout and discovered there are significant discrepancies between the submitted plans and the existing layout. These differences include, but are not limited to, corridors, rooms, and walls not shown on the plans, rooms shown on the plans that do not exist, etc... The plans must be resubmitted to accurately show the existing layout of the building. I met Stacey and made him aware of this information. At that time, he also said he's waiting to hear back regarding changing the FACP rather than replacing the existing smoke detectors.
|
Alarm Plan Check | 3/10/2010 | | 3/10/2010 | | FAIL |
Stephanie L. Cobbley
|
|
|
The plans submitted are significantly different than actual floorplan layout on the first floor. Resubmittal required to accurately show all corridors, rooms, walls, and open areas.
|
Telephone call | | | 3/10/2010 | | DONE |
|
|
|
Left a message for Mary letting her know the plans have been denied due to floorplan discrepencies. I let her know the plans and review comments would be at the front desk for her to pick up and that I would also be faxing her the review comments.
|
Miscellaneous action | | | 3/10/2010 | | DONE |
|
|
|
Faxed review comments to the contractor.
|
Miscellaneous action | | | 3/10/2010 | | DONE |
|
|
|
Recieved a fax from State Fire indicating the previously shown existing smoke detectors in the Coctail Lounge and Fitness area were originally shown by mistake and that they don't actually exist.
|
Plan resubmittals received | | | 3/9/2010 | | |
Tisha Gallop
|
|
|
received 1pg. letter from Mary Castle/Statefire DC Specialties. Taken to Steph Cobbley
|
Telephone call | | | 3/5/2010 | | DONE |
|
|
|
Spoke with Mary at State Fire to request documentation indicating why existing smoke detectors have been removed from the system.
|
Telephone call | | | 3/5/2010 | | DONE |
|
|
|
Stacey with Red Lion called to ask if he could try to get a different (new) FACP that is compatible with his existing smoke detectors rather than replace the existing smoke detectors to match the submitted (new) FACP. I told him that it was possible but he would need to work that out with the submitting contractor. He asked that I 'pause' the review while he looked in to his options. He let me know he'd try to call before the end of today.
|
Plan resubmittals received | | | 3/4/2010 | | |
Stephanie L. Cobbley
|
|
|
rec'd 2 sets
|
Early Start | | | 2/19/2010 | | DONE |
|
|
|
Approved an early start for the second elevator (see early start agreement #2)
|
Alarm Plan Check | 2/8/2010 | | 2/8/2010 | | FAIL |
Stephanie L. Cobbley
|
|
|
please see redlines and review comments
|
Miscellaneous action | | | 2/8/2010 | | DONE |
|
|
|
review comments faxed to contractor
|
Miscellaneous action | | | 2/8/2010 | | DONE |
|
|
|
denied redlined plans available at front counter for contractor pick up
|
Plan resubmittals received | | | 2/4/2010 | | |
|
|
|
received application and two copies of submittal folder and plans sheets FA1, FA2, FA3, FA4, FA5, FA6; taken to fire review
|
Miscellaneous action | | | 1/14/2010 | | DONE |
|
|
|
picked up denied plans
|
Early Start | | | 1/13/2010 | | DONE |
|
|
|
Early start agreement applies, see document
|
1st review completed | | | 1/13/2010 | | FAIL |
|
|
|
|
Alarm Plan Check | 1/13/2010 | | 1/13/2010 | | FAIL |
Stephanie L. Cobbley
|
|
|
Plans failed - see review comments and redlined plans
|
Miscellaneous action | | | 1/13/2010 | | DONE |
|
|
|
Faxed review comments to contractor and called Stacey with Redlion to update as requested.
|
Telephone call | | | 1/13/2010 | | DONE |
|
|
|
Called Billy at State Fire to let him know the plans would be denied and that he would be recieving a fax with the review comments. I let him know that as soon as he recieved the fax, he would know the redlined plans would be available for pick up.
|
Miscellaneous action | | | 1/13/2010 | | DONE |
|
|
|
Redlined plans placed in drawer at front counter for contractor pick up.
|
Application received | | | 1/8/2010 | | |
|
|
|
|