Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR10-00028
StatusFinaled
Name JBL FIRE PROTECTION LLC
Site Address 11818 W JOPLIN RD
Project NameWWTP Central Lab Addition
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of approximately 200'± 6" DI piping with associated fittings and thrust blocks. A new connection will made to the existing 4" riser. A new tree system will protect the new addition. The detection/releasing portion of the preaction system is under permit FIR10-00144

Plan Mod Scope:
The system piping arrangement was completely redesigned. It is now a double tree system with a 4" and 3" main.

Boise Public Works- West Boise Central Lab - Metals Lab Addition - To construct a 3,675 square foot, one story, wood framed addition on the west end of the existing West Boise Central Laboratory building and to do a small remodel within the existing building between grid lines 3 & 4 and B & D. This addition will include two new Metals Instruments Rooms, two new Preparation Rooms and two new Acid Wash Rooms, a new Mechanical Room, a new AWN Room and new entry. This addition will also have a five-foot high mechanical attic.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/13/20111/14/20111/14/2011APASS
DetailsTroy Cobbley
permit finaled.
Miscellaneous action  1/14/2011 DONE
Sent to records for scanning.
INSP-Final Inspection1/13/20111/13/20111/13/2011PCANC
DetailsTroy Cobbley
Canceled due to time constraints and Micron plan review
FIR-Aging Inspection1/3/20111/3/20111/10/2011 NR
DetailsTroy Cobbley
work is in progress
INSP-Sprinkler Rough-in11/2/201011/3/201011/3/2010PPASS
DetailsTroy Cobbley
The 24 hour air test passed
INSP-Sprinkler Rough-in11/1/201011/2/201011/2/2010APASS
DetailsTroy Cobbley
24 hr air test inspection started at 9:30 am with 46psi on the guage.
INSP-Sprinkler Rough-in/Hydro11/1/201011/1/201011/1/2010PPASS
DetailsTroy Cobbley
Overhead hydro test passed
INSP-Sprinkler Rough-in8/25/20108/25/20108/25/2010PPASS
DetailsTroy Cobbley
Above ground hydro test passed.
INSP-Sprinkler Rough-in/Hydro8/24/20108/25/20108/25/2010AFAIL
DetailsTroy Cobbley
Above ground hydro test failed. Earthquaking has been corrected and the FDC piping has been installed. Phone #: ###-####
INSP-Sprinkler Rough-in8/6/20108/6/20108/6/2010PPASS
DetailsTroy Cobbley
The rough-in inspection passed except for the earthquake bracing and the rerouted fire dept connection piping.
CHANGE STATUS TO (ISS)  8/6/2010 DONE
DetailsTisha Gallop
picked up and paid for plan mod
Sprinkler Plan Check7/16/2010 7/16/2010 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  7/16/2010 DONE
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  7/16/2010 DONE
DetailsTim Frost
Inspection Record Card- Fire7/16/2010 7/16/2010 DONE
DetailsPatricia Smith
Telephone call  7/16/2010 DONE
t/c w jonathan at ###-#### - permit (plan mod) ready and fees given
Permit Ready to Issue  7/16/2010 DONE
Details
Plan resubmittals received  7/15/2010 DONE
Received 3 sets of plan modification fire plans,sent to Tim Frost for review.///dld
Issue and Print Permit  5/11/2010  
Sprinkler Plan Check4/2/2010 4/5/2010 PASS
DetailsTim Frost
Sprinkler Plan reviewer approved submitted fire detection plans under FIR10-00144.
PLANS/APPL TAKEN TO FRONT DESK  4/5/2010 DONE
Inspection Record Card- Fire4/5/2010 4/5/2010 DONE
DetailsPatricia Smith
Telephone call  4/5/2010 DONE
left vm for jonathan at ###-#### - permit ready and fees given
Permit Ready to Issue  4/5/2010 DONE
Plan resubmittals received  2/19/2010  
DetailsTim Frost
rec'd 3 sets
Telephone call  2/19/2010 PEND
Review is complete except for the detection system. The submittal did not include the detection system. The review is on HOLD until the detection system has been reviewed. I have spoke to the contractor on several occasions regarding this matter. They are working with the alarm contractor to submit the detection system as soon as possible.
Plan assigned to (Tim)1/19/2010 1/21/2010 DONE
DetailsTim Frost
Sprinkler Plan Check1/21/2010 1/21/2010 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  1/21/2010 DONE
DetailsTim Frost
Telephone call  1/21/2010 DONE
Details
t/c w jonathan at ###-#### - permit denied - needs to be picked up and resubmitted
Application received  1/19/2010  
Pending Assignment by SAM1/19/2010 1/19/2010 DONE
DetailsAlexandra L. DeYoung
1/19/2010 15:02:59 ALR - activity updated through activity FIRA158 from case FIR10-00028.