INSP-Final Inspection | 1/13/2011 | 1/14/2011 | 1/14/2011 | A | PASS |
Troy Cobbley
|
|
|
permit finaled.
|
Miscellaneous action | | | 1/14/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 1/13/2011 | 1/13/2011 | 1/13/2011 | P | CANC |
Troy Cobbley
|
|
|
Canceled due to time constraints and Micron plan review
|
FIR-Aging Inspection | 1/3/2011 | 1/3/2011 | 1/10/2011 | | NR |
Troy Cobbley
|
|
|
work is in progress
|
INSP-Sprinkler Rough-in | 11/2/2010 | 11/3/2010 | 11/3/2010 | P | PASS |
Troy Cobbley
|
|
|
The 24 hour air test passed
|
INSP-Sprinkler Rough-in | 11/1/2010 | 11/2/2010 | 11/2/2010 | A | PASS |
Troy Cobbley
|
|
|
24 hr air test inspection started at 9:30 am with 46psi on the guage.
|
INSP-Sprinkler Rough-in/Hydro | 11/1/2010 | 11/1/2010 | 11/1/2010 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Sprinkler Rough-in | 8/25/2010 | 8/25/2010 | 8/25/2010 | P | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/24/2010 | 8/25/2010 | 8/25/2010 | A | FAIL |
Troy Cobbley
|
|
|
Above ground hydro test failed. Earthquaking has been corrected and the FDC piping has been installed. Phone #: ###-####
|
INSP-Sprinkler Rough-in | 8/6/2010 | 8/6/2010 | 8/6/2010 | P | PASS |
Troy Cobbley
|
|
|
The rough-in inspection passed except for the earthquake bracing and the rerouted fire dept connection piping.
|
CHANGE STATUS TO (ISS) | | | 8/6/2010 | | DONE |
Tisha Gallop
|
|
|
picked up and paid for plan mod
|
Sprinkler Plan Check | 7/16/2010 | | 7/16/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 7/16/2010 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/16/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 7/16/2010 | | 7/16/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 7/16/2010 | | DONE |
|
|
|
t/c w jonathan at ###-#### - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 7/16/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/15/2010 | | DONE |
|
|
|
Received 3 sets of plan modification fire plans,sent to Tim Frost for review.///dld
|
Issue and Print Permit | | | 5/11/2010 | | |
|
|
|
|
Sprinkler Plan Check | 4/2/2010 | | 4/5/2010 | | PASS |
Tim Frost
|
|
|
Sprinkler Plan reviewer approved submitted fire detection plans under FIR10-00144.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/5/2010 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/5/2010 | | 4/5/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 4/5/2010 | | DONE |
|
|
|
left vm for jonathan at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 4/5/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/19/2010 | | |
Tim Frost
|
|
|
rec'd 3 sets
|
Telephone call | | | 2/19/2010 | | PEND |
|
|
|
Review is complete except for the detection system. The submittal did not include the detection system. The review is on HOLD until the detection system has been reviewed. I have spoke to the contractor on several occasions regarding this matter. They are working with the alarm contractor to submit the detection system as soon as possible.
|
Plan assigned to (Tim) | 1/19/2010 | | 1/21/2010 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/21/2010 | | 1/21/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 1/21/2010 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 1/21/2010 | | DONE |
|
|
|
t/c w jonathan at ###-#### - permit denied - needs to be picked up and resubmitted
|
Application received | | | 1/19/2010 | | |
|
|
|
|
Pending Assignment by SAM | 1/19/2010 | | 1/19/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
1/19/2010 15:02:59 ALR - activity updated through activity FIRA158 from case FIR10-00028.
|