Miscellaneous action | | | 7/28/2010 | | DONE |
|
|
|
FA plans taken to records for scanning.
|
INSP-Final Inspection | 7/21/2010 | 7/22/2010 | 7/26/2010 | A | PASS |
Forrest France
|
|
|
Remainder of fire alarm system acceptance testing completed satisfactory. Fire alarm permit finaled.
|
INSP-Alarm Testing | 7/20/2010 | 7/20/2010 | 7/26/2010 | P | PART |
Forrest France
|
|
|
Completed fire sprinkler riser supervision interconnect testing including supervisory and alarm signals.
|
INSP-Final Inspection | 7/14/2010 | 7/16/2010 | 7/15/2010 | A | CANC |
Forrest France
|
|
|
Forrest, Please let me know an approximate time, so I can notify everyone associated. Thank you. Jason ###-#### Phone #: ###-#### >> Inspection requested via web by Jason Minnick Inspection cancelled from web by: Jason Minnick
|
FIR-Aging Inspection | 6/1/2010 | 6/1/2010 | 6/2/2010 | | DONE |
Forrest France
|
|
|
Work in progress, site construction underway.
|
Plan assigned to (Stephanie) | 1/26/2010 | | 3/2/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
3/2/2010 11:58:25 SLC - activity updated through activity FIRA24 from case FIR10-00038.
|
Alarm Plan Check | 3/2/2010 | | 3/2/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
approved - see review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 3/2/2010 | | DONE |
|
|
|
approved plans available at front counter
|
Inspection Record Card- Fire | 3/2/2010 | | 3/2/2010 | | DONE |
|
|
|
|
Telephone call | | | 3/2/2010 | | DONE |
|
|
|
t/c w lisa at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 3/2/2010 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/2/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/26/2010 | | |
Stephanie L. Cobbley
|
|
|
rec'd 2 sets
|
1st review completed | | | 2/2/2010 | | DONE |
|
|
|
|
Alarm Plan Check | 2/2/2010 | | 2/2/2010 | | FAIL |
Stephanie L. Cobbley
|
|
|
see redlines and review comments
|
Miscellaneous action | | | 2/2/2010 | | DONE |
|
|
|
faxed copy of review comments to contractor
|
Miscellaneous action | | | 2/2/2010 | | DONE |
|
|
|
redlined failed plans available at front counter for contractor pick up
|
Miscellaneous action | | | 2/2/2010 | | |
Tisha Gallop
|
|
|
picked up denied plans
|
Application received | | | 1/26/2010 | | |
|
|
|
|