Case Summary | | | 6/1/2016 | | DONE |
|
|
|
|
Miscellaneous action | | | 7/19/2010 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 3/29/2010 | 3/29/2010 | 3/29/2010 | P | PASS |
Forrest France
|
|
|
C/N items finished, fire sprinkler permit final approved.
|
INSP-Sprinkler Rough-in | 3/25/2010 | 3/25/2010 | 3/25/2010 | P | PART |
Forrest France
|
|
|
Ref. NFPA 13 sec. 8.16.4.2.3 regarding inspection activity notes.
|
INSP-Final Inspection | 3/24/2010 | 3/24/2010 | 3/24/2010 | P | PART |
Forrest France
|
|
|
Final pending protection of piping from corrosion where exposed at the outside of the building per NFPA 13 ch. 8 as discussed, also need to provide spare sprinkler stock of the new type installed at the head box. Remainder of overhead modifications and rough-in per the scope of work are satisfactory.
|
INSP-Final Inspection | 3/23/2010 | 3/23/2010 | 3/23/2010 | P | CANC |
Forrest France
|
|
|
Jim Phone #: ###-#### Inspection to be rescheduled per conversation with contractor.
|
Sprinkler Plan Check | 2/8/2010 | | 2/8/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/8/2010 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 2/8/2010 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 2/8/2010 | | DONE |
Bethany Sullins
|
|
|
Called and left message with Veronica that plans are ready & fees due @ 11:15am on 2-8-10 BAS
|
Issue and Print Permit | | | 2/8/2010 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 2/1/2010 | | 2/8/2010 | | DONE |
Tim Frost
|
|
|
2/8/2010 10:08:32 TRF - activity updated through activity FIRA22 from case FIR10-00042.
|
Plan resubmittals received | | | 2/5/2010 | | |
Tim Frost
|
|
|
rec'd 3 sets
|
Plan assigned to (Tim) | 1/28/2010 | | 2/1/2010 | | DONE |
Tim Frost
|
|
|
2/1/2010 09:16:17 TRF - activity updated through activity FIRA22 from case FIR10-00042.
|
Sprinkler Plan Check | 2/1/2010 | | 2/1/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 2/1/2010 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 2/1/2010 | | DONE |
|
|
|
Emailed comment to contractor and designer.
|
Telephone call | | | 2/1/2010 | | DONE |
|
|
|
left message w vanessa for jim danes at ###-#### - permit denied - needs to be picked up and resubmitted
|
Application received | | | 1/28/2010 | | |
|
|
|
|
Case Summary | | | 1/28/2010 | | DONE |
|
|
|
|