Miscellaneous action | | | 3/2/2010 | | DONE |
|
|
|
fire alarm plans taken to records for scanning
|
INSP-Final Inspection | 2/12/2010 | 2/12/2010 | 2/12/2010 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Sync modules were installed and setup while I waited. I let Tom know that I would need as-builts showing the addition of the sync modules.
|
CHANGE STATUS TO (ISS) | | | 2/12/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/11/2010 | | |
Tisha Gallop
|
|
|
received two copies of fire alarm data sheets and revised battery calcs; taken to fire review
|
Plan assigned to (Stephanie) | 2/11/2010 | | 2/11/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
2/11/2010 15:54:22 SLC - activity updated through activity FIRA24 from case FIR10-00046.
|
Alarm Plan Check | 2/11/2010 | | 2/11/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
new cut sheets and calcs - replacing 'new' devices with different model number (same manufactuer). No additional review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 2/11/2010 | | DONE |
|
|
|
approved set available at front counter
|
Telephone call | | | 2/11/2010 | | DONE |
|
|
|
t/c w joe at ###-#### - permit (plan mod #2) ready
|
Plan resubmittals received | | | 2/10/2010 | | DONE |
|
|
|
rec'd 2 sets of fire alarm data sheets and revised battery calculations - taken to stephanie cobbley
|
Plan assigned to (Stephanie) | 2/10/2010 | | 2/10/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
2/10/2010 10:27:48 SLC - activity updated through activity FIRA24 from case FIR10-00046.
|
Alarm Plan Check | 2/10/2010 | | 2/10/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
Approved -see scope of work for plan modification information. Original review comments dated 2/4/10 still apply. No additional review comments necessary.
|
PLANS TAKEN FRONT DESK ALARM | | | 2/10/2010 | | DONE |
|
|
|
approved set available at front counter
|
Permit Ready to Issue | | | 2/10/2010 | | DONE |
|
|
|
|
Telephone call | | | 2/10/2010 | | DONE |
|
|
|
left vm for ken at ###-#### - permit (plan mod) ready
|
INSP-Final Inspection | 2/8/2010 | 2/8/2010 | 2/8/2010 | P | FAIL |
Troy Cobbley
|
|
|
Change the text as discussed on the facp display to include the smoke detectors in the new bedrooms, provide sync on the horn as per nfpa 72 a6.8.6.5.3, battery and NAC circuits did not report a trouble at the facp from the NAC panel.
|
INSP-Final Inspection | 2/8/2010 | 2/9/2010 | 2/8/2010 | A | CANC |
Troy Cobbley
|
|
|
Tom Wahl Phone #: ###-#### Internet Inspection Request from: joe fink Inspection cancelled from web by: joe fink
|
Issue and Print Permit | | | 2/8/2010 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 2/1/2010 | | 2/4/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
2/4/2010 15:36:42 SLC - activity updated through activity FIRA24 from case FIR10-00046.
|
1st review completed | | | 2/4/2010 | | DONE |
|
|
|
|
Alarm Plan Check | 2/4/2010 | | 2/4/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
see redlines and review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 2/4/2010 | | DONE |
|
|
|
approved redlined plans available at front counter
|
Inspection Record Card- Fire | 2/4/2010 | | 2/4/2010 | | DONE |
|
|
|
|
Telephone call | | | 2/4/2010 | | DONE |
|
|
|
t/c w ken at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 2/4/2010 | | DONE |
|
|
|
|
Application received | | | 2/1/2010 | | |
|
|
|
|