Miscellaneous action | | | 7/28/2010 | | DONE |
|
|
|
FA plans taken to records for scanning.
|
INSP-Final Inspection | 7/27/2010 | 7/27/2010 | 7/27/2010 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Alarm Testing | 5/27/2010 | 5/28/2010 | 5/28/2010 | A | DONE |
Troy Cobbley
|
|
|
Phase I fire alarm is complete.
|
INSP-Alarm Testing | 5/26/2010 | 5/27/2010 | 5/27/2010 | A | CANC |
Troy Cobbley
|
|
|
Rescheduled for tomorrow morning
|
INSP-Alarm Testing | 5/25/2010 | 5/26/2010 | 5/26/2010 | A | DONE |
Troy Cobbley
|
|
|
The items previously listed have been corrected. Duct smoke detectors have been tested for hvac shutdown. EOL voltage was verified. Two smoke detectors were tested for operation that operate roll down fire doors. They were not approved for location only for function. They are not shown on the city approved plans. They are to be included on the revised plans. Items remaining for phase I include the 135cd strobe and the repair of the corridor roll down fire door.
|
INSP-Alarm Testing | 5/24/2010 | 5/24/2010 | 5/24/2010 | P | DONE |
Troy Cobbley
|
|
|
Some of the phase I items were tested today. They included verification of the FACP model, telephone line numbers and troubles, facp battery trouble and interconnection with the NAC in the phase I basement. Spacing and operation of the phase I a/v's were also tested. A weather proof back box is needed at the cart ramp, add a strobe in the dressing room, provide a 135cd strobe in the outside dining area and provide the corrected sample tubes for the duct smoke detectors. The a/v's will need to be retested and EOL verified, test the duct smoke detectors for hvac shutdown, test the new smoke detectors and pull station.
|
INSP-Alarm Testing | 5/13/2010 | 5/14/2010 | 5/14/2010 | A | PASS |
Troy Cobbley
|
|
|
The fire alarm system in Phase 2 pool/restrooms is complete and tested ok. Additional strobe were required/added in the showers and restoom stalls. They will need to be shown on the resubmitted plans or as-builts which ever case it may be.
|
INSP-Alarm Testing | 5/11/2010 | 5/12/2010 | 5/12/2010 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for the five rooms at the pool area. They include locker/showers and restrooms. The visual coverage is inadequate due to alot of shadowing. It appears that atleast seven additional strobes are going to be required. EOL will need to be verified on this circuit when the fire alarm system installation has been completed.
|
Issue and Print Permit | | | 2/25/2010 | | DONE |
|
|
|
|
Alarm Plan Check | 2/24/2010 | | 2/24/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
see redlines and review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 2/24/2010 | | DONE |
|
|
|
approved redlined plans available at front counter
|
Inspection Record Card- Fire | 2/24/2010 | | 2/24/2010 | | DONE |
|
|
|
|
Telephone call | | | 2/24/2010 | | DONE |
|
|
|
t/c w shelly at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 2/24/2010 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 2/10/2010 | | 2/24/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
2/24/2010 13:16:00 SLC - activity updated through activity FIRA24 from case FIR10-00060.
|
Plan resubmittals received | | | 2/18/2010 | | |
Tisha Gallop
|
|
|
received one plan sheet inserted into plans by Protex rep.//taken to fire review
|
Miscellaneous action | | | 2/17/2010 | | DONE |
|
|
|
Faxed review comments to Protex as no fax number was provided for the applicant.
|
Plan resubmittals received | | | 2/17/2010 | | |
Stephanie L. Cobbley
|
|
|
|
1st review completed | | | 2/17/2010 | | DONE |
|
|
|
|
Alarm Plan Check | 2/17/2010 | | 2/17/2010 | | FAIL |
Stephanie L. Cobbley
|
|
|
See redlines and review comments
|
Miscellaneous action | | | 2/17/2010 | | DONE |
|
|
|
redlined plans available at front counter for contractor to pick up
|
Telephone call | | | 2/16/2010 | | DONE |
|
|
|
Spoke to Rob with Protex and let him know that I could either reject the plans, he can pick them up, revise them, and resubmit (one permit fee); or I could go ahead and approve them but that he would need to resubmit a plan modification prior to calling for a final inspection (two permit fees). He opted to have me reject the plans.
|
Application received | | | 2/10/2010 | | |
|
|
|
|