Miscellaneous action | | | 6/8/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 3/29/2011 | 3/30/2011 | 3/30/2011 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
FIR-Aging Inspection | 3/29/2011 | 3/29/2011 | 3/30/2011 | | PASS |
Troy Cobbley
|
|
|
|
INSP-Final Inspection | 1/27/2011 | 1/27/2011 | 1/27/2011 | P | PART |
Tim Frost
|
|
|
This inspection was called in under the wrong permit BLD10-00114.
The exterior canopy was inspected. The canopy is completely filled with non-combustible insulation. I gave then the ok to cover the canopy with hardy board. Therefore no sprinkler was required.
|
Inspection | 1/28/2011 | 1/27/2011 | 1/27/2011 | A | PART |
Tim Frost
|
|
|
|
Miscellaneous action | | | 1/3/2011 | | DONE |
|
|
|
Received a letter from John McCarthy with Eireannach. Indicating that all exposed surfaces of the entrance foyer will be non-combustible therefore, not requiring a sprinkler. He also indicated and reemphasized that the attic space must be entirely filled with non combustible insulation. I also, mentioned in the email that a space must be left open in the canopy so that the field inspector may be to able to visually veify the space. Please, see the case file for details.
|
INSP-Final Inspection | 12/8/2010 | 12/8/2010 | 12/8/2010 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given, with Scott's permission, until the front entry canopy is complete and the additional fire sprinkler is installed.
|
INSP-Final Inspection | 12/2/2010 | 12/3/2010 | 12/3/2010 | A | FAIL |
Troy Cobbley
|
|
|
Need to perform a job walk through and verify there are no head obstructions, need all of the final items at the riser such as backflow certification, head box, stickers...ect. Also noted that a pendant head was installed in the electrical room but a ceiling had not been installed.
|
INSP-Supply line flush | 12/2/2010 | 12/3/2010 | 12/3/2010 | A | PASS |
Troy Cobbley
|
|
|
supply line flush passed.
|
INSP-Sprinkler Rough-in | 12/2/2010 | 12/3/2010 | 12/3/2010 | A | PASS |
Troy Cobbley
|
|
|
The underground flush passed and the forward flush test of the backflow preventor passed.
|
INSP-Sprinkler Rough-in/Hydro | 12/2/2010 | 12/2/2010 | 12/2/2010 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/19/2010 | 10/20/2010 | 10/20/2010 | A | PASS |
Troy Cobbley
|
|
|
The under ground hydro passed. No flush was performed.
|
INSP-Sprinkler Rough-in | 10/14/2010 | 10/15/2010 | 10/15/2010 | A | PASS |
Troy Cobbley
|
|
|
The underground supply piping is ok to cover.
|
Override - Parcel Holds | 10/14/2010 | 1/1/1900 | 10/14/2010 | | |
|
|
|
fire only
|
INSP-Sprinkler Rough-in | 8/25/2010 | 8/25/2010 | 8/25/2010 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping in the high ceiling area, as discussed, can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 8/19/2010 | 8/19/2010 | 8/19/2010 | P | PASS |
Troy Cobbley
|
|
|
Piping rough-in passed except for the two clouded areas marked on the plan in red where the piping has not been installed yet. Also one upright head is blocked by truss web members and is to be relocated as discussed. As-built plans will be required showing the piping routing changes. A hydro test was not performed since the upright needs relocated and none of the permanant sprinkler pendants/sidewalls have been installed. Branch line restraints have not been installed and the longitudinal earthquake bracing has not been installed. The insulation will be required to be installed at the deck since the upright sprinkler heads are located too far below the wood deck.
|
CHANGE STATUS TO (ISS) | | | 8/19/2010 | | |
|
|
|
|
(F) Reprint permit | | | 8/19/2010 | | |
|
|
|
|
Plan assigned to (Tim) | 8/10/2010 | | 8/11/2010 | | DONE |
Tim Frost
|
|
|
8/11/2010 13:46:34 TRF - activity updated through activity FIRA22 from case FIR10-00072.
|
Plan resubmittals received | | | 8/11/2010 | | |
|
|
|
received 3 sets of plans/applications sent to Tim Frost for review
|
Sprinkler Plan Check | 8/11/2010 | | 8/11/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/11/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 8/11/2010 | | 8/11/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 8/11/2010 | | DONE |
|
|
|
t/c w don at ###-#### - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 8/11/2010 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/10/2010 | | 8/10/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 8/10/2010 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 8/10/2010 | | DONE |
|
|
|
t/c w don at ###-#### - permit (plan mod) denied - needs to be picked up and resubmitted
|
Plan resubmittals received | | | 8/10/2010 | | DONE |
Tisha Gallop
|
|
|
Plan Modification: Received three copies of application, submittal documents and plans; taken to Fire Review
|
FIR-Aging Inspection | 7/9/2010 | 7/9/2010 | 7/9/2010 | | NR |
Troy Cobbley
|
|
|
Work is in progress
|
Issue and Print Permit | | | 3/11/2010 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/10/2010 | | 3/10/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/10/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 3/10/2010 | | 3/10/2010 | | DONE |
|
|
|
|
Telephone call | | | 3/10/2010 | | DONE |
|
|
|
t/c w don at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 3/10/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/9/2010 | | DONE |
|
|
|
received 4 resumittal plans and apps sent to Tim Frost
|
Sprinkler Plan Check | 3/4/2010 | | 3/4/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
Miscellaneous action | | | 3/4/2010 | | DONE |
|
|
|
Emailed 2nd review
|
Telephone call | | | 3/4/2010 | | DONE |
|
|
|
t/c w don at ###-#### - permit denied - needs to be picked up and resubmitted
|
Plan resubmittals received | | | 3/2/2010 | | |
Tim Frost
|
|
|
received four copies of application, checklist, submittal documents and plan sheets FP-01, FP-02; taken to fire review
|
Plan assigned to (Tim) | 2/18/2010 | | 2/19/2010 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/19/2010 | | 2/19/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 2/19/2010 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 2/19/2010 | | DONE |
|
|
|
Emailed comments
|
Telephone call | | | 2/19/2010 | | DONE |
|
|
|
t/c w don at ###-#### - permit denied - needs to be picked up and resubmitted
|
Application received | | | 2/18/2010 | | |
|
|
|
|
Pending Assignment by SAM | 2/18/2010 | | 2/18/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
2/18/2010 13:50:30 ALR - activity updated through activity FIRA158 from case FIR10-00072.
|