Miscellaneous action | | | 12/2/2010 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 10/27/2010 | 10/29/2010 | 10/29/2010 | A | PASS |
Forrest France
|
|
|
Items on correction notice are finished. Fire alarm permit finaled. Inspection passed.
|
INSP-Final Inspection | 8/2/2010 | 8/2/2010 | 8/2/2010 | P | FAIL |
Troy Cobbley
|
|
|
Provide as-built drawings showing the additional fifteen existing duct smoke detectors, test all of the duct smoke detectors, provide verification of code compliant installation of the duct detectors (location & immediate shutdown), provide signage as per the review comment #30, provide map at the facp/annunciator as per review note #28, provide copy of the test signals from today.
|
INSP-Conference | 6/15/2010 | 6/15/2010 | 6/16/2010 | P | DONE |
Troy Cobbley
|
|
|
Art and I discussed the locations of the existing fire alarm devices. I told him unless they meet the requirements of a previous code the mounting heights will have to conform to current code.
|
Issue and Print Permit | | | 6/14/2010 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/9/2010 | | 6/9/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 6/9/2010 | | DONE |
|
|
|
t/c w keith at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 6/9/2010 | | DONE |
|
|
|
|
1st review completed | | | 6/8/2010 | | DONE |
|
|
|
|
Alarm Plan Check | 6/8/2010 | | 6/8/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
see redlines and review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 6/8/2010 | | DONE |
|
|
|
approved redlined drawings available at front counter
|
Plan assigned to (Stephanie) | 5/17/2010 | | 6/8/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
6/8/2010 15:43:08 SLC - activity updated through activity FIRA24 from case FIR10-00231.
|
Plan resubmittals received | | | 6/7/2010 | | DONE |
Tisha Gallop
|
|
|
received application and two copies of submittal documents and plan sheet ADT-FA-01; taken to Fire Review.
|
1st review completed | | | 5/26/2010 | | DONE |
|
|
|
|
Alarm Plan Check | 5/26/2010 | | 5/26/2010 | | FAIL |
Stephanie L. Cobbley
|
|
|
see review comments and redlined plans
|
Miscellaneous action | | | 5/26/2010 | | DONE |
|
|
|
faxed review comments to applicant
|
Telephone call | | | 5/26/2010 | | DONE |
|
|
|
left a message for Keith letting him know the plans are denied.
|
Miscellaneous action | | | 5/26/2010 | | DONE |
|
|
|
Due to working without a permit, a double fee will be applied once the review has been completed.
|
Miscellaneous action | | | 5/26/2010 | | DONE |
|
|
|
the redlined plans and review comments are available at the front counter for customer pick up.
|
Telephone call | | | 5/25/2010 | | DONE |
|
|
|
Spoke to Kieth with ADT and let him know I need a one-line/riser diagram for the fire alarm system. I advised him that I would need two copies of the one-line by Friday or I would need to fail the plans. He stated he understood and would get with the engineer right away.
|
Application received | | | 5/17/2010 | | |
|
|
|
|