Miscellaneous action | | | 6/8/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 2/8/2011 | 2/9/2011 | 2/9/2011 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. 200 degree pendants have been provided at the supply diffusers per Rick.
|
INSP-Sprinkler Rough-in | 12/22/2010 | 12/22/2010 | 12/22/2010 | P | PASS |
Troy Cobbley
|
|
|
The remaining sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 12/8/2010 | 12/8/2010 | 12/8/2010 | P | PART |
Forrest France
|
|
|
Overhead fire sprinkler work at the two window bays and one pendent head at the partition wall storage cubby in the private dining area phase two okayed for ceiling cover.
|
INSP-Sprinkler Rough-in | 10/26/2010 | 10/27/2010 | 10/27/2010 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping above the private dining area is ok to cover. Coverage has not been provided yet in the accordian wall pocket.
|
INSP-Sprinkler Rough-in/Hydro | 10/20/2010 | 10/20/2010 | 10/20/2010 | P | PASS |
Troy Cobbley
|
|
|
The new drops/arm-overs in the lay-in ceiling tile areas are ok to cover. Also the overhead hydro test of the new sprinkler piping passed.
|
INSP-Sprinkler Rough-in | 10/18/2010 | 10/18/2010 | 10/19/2010 | P | PASS |
Troy Cobbley
|
|
|
Rick provided the insulation behind the beam as discussed. The soffit can be covered. Also the three sprinkler pendants located in the womens restroom are passed.
|
INSP-Sprinkler Rough-in | 10/14/2010 | 10/14/2010 | 10/14/2010 | P | PASS |
Troy Cobbley
|
|
|
Rick and I discussed areas where sprinkler piping could be covered.
|
INSP-Sprinkler Rough-in | 10/11/2010 | 10/12/2010 | 10/12/2010 | A | PASS |
Troy Cobbley
|
|
|
Rough-in of the sprinkler piping mostly passed. See the city approved plans for phase II where there are some small areas not yet complete. Insulation needs to be repaired in the existing areas and the insulation needs to be installed in the new areas. I noted atleast two areas created by beams and ducting where additional sprinkler piping will be needed or non-combustible insulation could be added. Insulation will need to be verified prior to a approval for cover being given.
|
INSP-Final Inspection | 7/8/2010 | 7/12/2010 | 7/12/2010 | A | FAIL |
Troy Cobbley
|
|
|
the forward flush test failed again
|
Plan assigned to (Tim) | 5/21/2010 | | 5/24/2010 | | DONE |
Tim Frost
|
|
|
5/24/2010 10:43:08 TRF - activity updated through activity FIRA22 from case FIR10-00236.
|
Sprinkler Plan Check | 5/24/2010 | | 5/24/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS TAKEN FRONT DESK ALARM | | | 5/24/2010 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 5/24/2010 | | 5/24/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 5/24/2010 | | DONE |
|
|
|
t/c w jeff at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 5/24/2010 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/24/2010 | | DONE |
|
|
|
|
Application received | | | 5/21/2010 | | |
|
|
|
|
Pending Assignment by SAM | 5/21/2010 | | 5/21/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
5/21/2010 14:11:24 ALR - activity updated through activity FIRA158 from case FIR10-00236.
|