Miscellaneous action | | | 1/14/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 11/4/2010 | 11/4/2010 | 11/4/2010 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 10/15/2010 | 10/15/2010 | 10/15/2010 | P | FAIL |
Troy Cobbley
|
|
|
Will be able to final when the insulation is repaired throughout the warehouse.
|
Inspection Record Card- Fire | 9/20/2010 | | 9/20/2010 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 9/20/2010 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 9/20/2010 | | DONE |
Barbara Stitt
|
|
|
Called JIm Darr and told him that permit is ready on 9-20-10 @ 8:55am
|
Issue and Print Permit | | | 9/20/2010 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 9/16/2010 | | 9/17/2010 | | DONE |
Tim Frost
|
|
|
9/17/2010 14:07:21 TRF - activity updated through activity FIRA22 from case FIR10-00238.
|
Sprinkler Plan Check | 9/17/2010 | | 9/17/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 9/17/2010 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/17/2010 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 9/16/2010 | | |
Tim Frost
|
|
|
plan mod -rec'd 3 sets
|
INSP-Final Inspection | 9/3/2010 | 9/7/2010 | 9/7/2010 | A | FAIL |
Troy Cobbley
|
|
|
The previous wall/draft stop/ needs to be removed out in the warehouse area and Storage Room 115 sprinkler pendants are too far down from the deck but still installed 8" above the t-bar/ceiling. Also in this room the flex ducting is creating alot of obstructions to the sprinkler coverage.
|
Plan assigned to (Tim) | 8/20/2010 | | 8/23/2010 | | DONE |
Tim Frost
|
|
|
8/23/2010 08:24:21 TRF - activity updated through activity FIRA22 from case FIR10-00238.
|
Sprinkler Plan Check | 8/23/2010 | | 8/23/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 8/23/2010 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 8/23/2010 | | 8/23/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 8/23/2010 | | DONE |
|
|
|
t/c w jim darr at ###-#### - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 8/23/2010 | | DONE |
|
|
|
|
(F) Reprint permit | | | 8/23/2010 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 8/23/2010 | | |
|
|
|
|
Plan resubmittals received | | | 8/20/2010 | | DONE |
Tisha Gallop
|
|
|
Plan Modification: Received three copies of application, submittal binder and plans; taken to Fire Review
|
INSP-Sprinkler Rough-in/Hydro | 8/4/2010 | 8/4/2010 | 8/4/2010 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro tests of both systems passed.
|
INSP-Sprinkler Rough-in | 8/2/2010 | 8/2/2010 | 8/2/2010 | P | PART |
Troy Cobbley
|
|
|
Need to remove the smoke curtain/draft stop. Need hydro test. Need the "load splitters" hanger assemblies for the main addressed per tim frost. On closet on the second floor has a ceiling and has not been provided sprinkler protection. Also the sprinkler piping located above the first floor ceiling in the office area needs inspection.
|
INSP-Sprinkler Rough-in/Hydro | 7/29/2010 | 7/30/2010 | 7/30/2010 | A | CANC |
Troy Cobbley
|
|
|
justin Phone #: ###-####//cancelled per Justin 7/30 @ 7:18am
|
INSP-Sprinkler Rough-in | 7/29/2010 | 7/29/2010 | 7/29/2010 | P | CANC |
Troy Cobbley
|
|
|
Cancelled due to time constraints caused by Micron plan review. Will be rescheduled for tomorrow per the fitter.
|
Inspection Record Card- Fire | 5/26/2010 | | 5/26/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 5/26/2010 | | DONE |
|
|
|
t/c w jim darr at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 5/26/2010 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/26/2010 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 5/24/2010 | | 5/25/2010 | | DONE |
Tim Frost
|
|
|
5/25/2010 16:07:00 TRF - activity updated through activity FIRA22 from case FIR10-00238.
|
Telephone call | | | 5/25/2010 | | DONE |
|
|
|
Per a phone call with the Fire Marshal. Mr. Mark Senteno he approved the building access as is. Mr. Senteno also approved the existing doors as is. Therefore no new doors are required.
|
Miscellaneous action | | | 5/25/2010 | | DONE |
|
|
|
Email from Jeff Packham @ Treasure Valley Fire Protection
They will be storing on the racks the following:
Coca products packaged, cartoned.
Powders ordinary combustibles---free flowing-In paper bags (e.g., flours, sugar).
Empty Plastic cottage cheese containers Group A Plastics.
Cartons unassembled neatly piled.
All of the items are stored in the same manner, up to multi row racks, no more than 25' high, with open shelves. The higher hazard sprinkler protection of the group A plastics was determined to protect all of the lesser hazard commodities.
|
Sprinkler Plan Check | 5/25/2010 | | 5/25/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 5/25/2010 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/25/2010 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 5/24/2010 | | |
|
|
|
|
Pending Assignment by SAM | 5/24/2010 | | 5/24/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
5/24/2010 16:01:34 ALR - activity updated through activity FIRA158 from case FIR10-00238.
|