Miscellaneous action | | | 9/8/2010 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 7/12/2010 | 7/12/2010 | 7/12/2010 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 7/7/2010 | 7/8/2010 | 7/8/2010 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given on this permit with Marks permission until the two sprinkler heads are installed in the conveyor.
|
INSP-Sprinkler Rough-in | 6/29/2010 | 6/29/2010 | 6/29/2010 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping in the office areas can be covered.
|
INSP-Sprinkler Rough-in | 6/15/2010 | 6/15/2010 | 6/15/2010 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping above the hardlids is ok to cover. Hangers and piping at other locations passed. Final sprinkler pendant spacing will be verified during another rough-in inspection.
|
Issue and Print Permit | | | 6/4/2010 | | |
|
|
|
|
Plan assigned to (Tim) | 5/28/2010 | | 6/2/2010 | | DONE |
Tim Frost
|
|
|
6/2/2010 14:19:49 TRF - activity updated through activity FIRA22 from case FIR10-00245.
|
Sprinkler Plan Check | 6/2/2010 | | 6/2/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 6/2/2010 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/2/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 6/2/2010 | | 6/2/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 6/2/2010 | | DONE |
|
|
|
t/c w lisa at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 6/2/2010 | | DONE |
|
|
|
|
Application received | | | 5/28/2010 | | |
|
|
|
|
Pending Assignment by SAM | 5/28/2010 | | 5/28/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
5/28/2010 09:44:28 ALR - activity updated through activity FIRA158 from case FIR10-00245.
|