Permit Information
Permit NumberFIR10-00245
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 10335 W EMERALD ST
Project NameEMERALD TECH BLDG 10
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of tenant improvement to an existing facility. The existing fire protection was designed for light hazard (225 Sqft) at the roof of an approximately 19' high building. The tenant will be electronic manufacturing (ordinary hazard group I), storage of class IV commodities (PVC-covered wire on plastic spools) and class III commodity (PVC-cabling) the storage is to not exceed 10' high. The existing sprinklers will be removed. New quick response sprinklers will be respaced at the roof to a maximum of 126 Sqft utilizing mechanical tees. There is an office area in the north end of the building, which will have, above and below protection. The below protection is based on light hazard (225 Sqft). The existing system has 6" C-900 underground, 3" main riser, 3" back flow preventer, 4" feed main, 3" cross main and 1½" branch lines. The main riser in located in a 1 hr rated room.

(PRECO ELECTRONICS (BUILDING 10) First time build-out and finish of 12,321 sq. ft. SHELL building (BLD06-01811) for use as Manufacturing Facility with Production/Radar Range, Packaging, R& D Radar Range, Support Administration, Lunch Room, Conference Room, Lobby & Accessible Restrooms, per approved plans. Work to include construction of interior non-bearing walls to create noted rooms and areas; suspended ceiling grid in specified areas, interior millwork, interior finishes and electrical, mechanical, plumbing, sprinkler and alarm systems per code. Drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  9/8/2010 DONE
Sent to records for scanning.
INSP-Final Inspection7/12/20107/12/20107/12/2010PPASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection7/7/20107/8/20107/8/2010APART
DetailsTroy Cobbley
A temporary occupancy was given on this permit with Marks permission until the two sprinkler heads are installed in the conveyor.
INSP-Sprinkler Rough-in6/29/20106/29/20106/29/2010PPASS
DetailsTroy Cobbley
The sprinkler piping in the office areas can be covered.
INSP-Sprinkler Rough-in6/15/20106/15/20106/15/2010PPASS
DetailsTroy Cobbley
The sprinkler piping above the hardlids is ok to cover. Hangers and piping at other locations passed. Final sprinkler pendant spacing will be verified during another rough-in inspection.
Issue and Print Permit  6/4/2010  
Plan assigned to (Tim)5/28/2010 6/2/2010 DONE
DetailsTim Frost
6/2/2010 14:19:49 TRF - activity updated through activity FIRA22 from case FIR10-00245.
Sprinkler Plan Check6/2/2010 6/2/2010 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  6/2/2010 DONE
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  6/2/2010 DONE
DetailsTim Frost
Inspection Record Card- Fire6/2/2010 6/2/2010 DONE
DetailsPatricia Smith
Telephone call  6/2/2010 DONE
t/c w lisa at ###-#### - permit ready and fees given
Permit Ready to Issue  6/2/2010 DONE
Details
Application received  5/28/2010  
Pending Assignment by SAM5/28/2010 5/28/2010 DONE
DetailsAlexandra L. DeYoung
5/28/2010 09:44:28 ALR - activity updated through activity FIRA158 from case FIR10-00245.