INSP-Final Inspection | 11/18/2010 | 11/18/2010 | 11/19/2010 | A | PASS |
Forrest France
|
|
|
Remainder of fire alarm work passed field testing. Permit finaled.
|
FIR-Aging Inspection | 11/11/2010 | 11/11/2010 | 11/15/2010 | | DONE |
Forrest France
|
|
|
In progress
|
INSP-Alarm Testing | 8/31/2010 | 9/1/2010 | 9/2/2010 | A | PART |
Forrest France
|
|
|
Completed notification testing at the 1st and 2nd floor per scope of permit work, also tested smoke detection at RF21, 16 and 26. FCU's are not yet installed.
|
Issue and Print Permit | | | 6/4/2010 | | DONE |
|
|
|
|
1st review completed | | | 6/3/2010 | | DONE |
|
|
|
|
Alarm Plan Check | 6/3/2010 | | 6/3/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
Approved per site review-see redlined plans regarding fire/smoke damper shutdown
|
PLANS TAKEN FRONT DESK ALARM | | | 6/3/2010 | | DONE |
|
|
|
|
Application received | | | 6/2/2010 | | DONE |
Mary Froemke
|
|
|
This permit was created on the web by Paul Marcolina
|
Application received | | | 6/2/2010 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|