INSP-Final Inspection | 9/27/2010 | 9/29/2010 | 9/29/2010 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit final approved. Two new sw heads to be verified at FLS final.
|
CHANGE STATUS TO (ISS) | | | 9/7/2010 | | DONE |
|
|
|
per slc
|
Sprinkler Plan Check | 9/3/2010 | | 9/3/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved per site inspection by T. Cobbley
|
PLANS TAKEN FRONT DESK ALARM | | | 9/3/2010 | | DONE |
|
|
|
|
INSP-Final Inspection | 8/31/2010 | 9/1/2010 | 9/2/2010 | A | PART |
Forrest France
|
|
|
Fire sprinkler work at the beam rooms are complete- need to verify resubmittals for field modifications. 2nd floor work incomplete at this time.
|
INSP-Sprinkler Rough-in | 8/16/2010 | 8/18/2010 | 8/18/2010 | A | PART |
Forrest France
|
|
|
Preliminary rough-in inspection completed for the two EBeam suites. Resubmittals pending for field modifications in branchline routing.
|
CHANGE STATUS TO (ISS) | | | 7/6/2010 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/1/2010 | | 7/1/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved per site review by Troy Cobbley
|
1st review completed | | | 7/1/2010 | | DONE |
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 7/1/2010 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/10/2010 | | 6/10/2010 | | PASS |
Troy Cobbley
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/10/2010 | | DONE |
Tim Frost
|
|
|
|
Issue and Print Permit | | | 6/10/2010 | | DONE |
|
|
|
|
1st review completed | | | 6/3/2010 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/3/2010 | | 6/3/2010 | | FAIL |
Stephanie L. Cobbley
|
|
|
Per site plan review, sprinkler heads are overspaced. Collin will verify and add heads.
|
Plan assigned to (Scott) | | | 6/2/2010 | | DONE |
Bill Alexander
|
|
|
This permit was created on the web by Paul Marcolina
|
Application received | | | 6/2/2010 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|