Miscellaneous action | | | 12/2/2010 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 10/27/2010 | 10/27/2010 | 10/28/2010 | P | PASS |
Forrest France
|
|
|
Fire alarm permit work passed inspection, some adjustments made while on site. Permit finaled.
|
CHANGE STATUS TO (ISS) | | | 10/26/2010 | | DONE |
|
|
|
picked up approved plan mod
|
Plan assigned to (Stephanie) | 10/20/2010 | | 10/25/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | 10/25/2010 | | 10/25/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
Plan modifications approved with redlines and review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 10/25/2010 | | DONE |
|
|
|
Approved plan modification plans available at front counter
|
Inspection Record Card- Fire | 10/25/2010 | | 10/25/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 10/25/2010 | | DONE |
|
|
|
left vm for phil at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/25/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/20/2010 | | DONE |
Tisha Gallop
|
|
|
Plan Modification: received one copy of application and checklist, two copies of battery calcs and plan; taken to Fire Review.
|
FIR-Aging Inspection | 9/22/2010 | 9/22/2010 | 9/22/2010 | | DONE |
Forrest France
|
|
|
Work in progress, construction underway.
|
Issue and Print Permit | | | 6/23/2010 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 6/7/2010 | | 6/14/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
6/14/2010 13:59:18 SLC - activity updated through activity FIRA24 from case FIR10-00260.
|
Miscellaneous action | | | 6/14/2010 | | DONE |
|
|
|
Received a forwarded email from Phil at Tristate with confirmation from Mark G. at CSHQA that the drawings have been reviewed and has found them to be acceptable.
|
Telephone call | | | 6/14/2010 | | DONE |
|
|
|
Spoke with Phil Bassick at Tri State Electric regarding the plans. There is a releasing system shown in the sprinkler system submittals that is not indicated in the fire alarm plans. I gave him the option of either resubmitting plans showing the connections and added smoke detector, or providing a plan modification prior to calling for an inspection. I explained that the plan modification would involve additional fees, but that he would be able to get going on the work now with approved drawings. He opted to have the plans approved with the understanding a plan modification (incorporating the redlines, review comments, and field modifications) would need to be submitted and approved prior to calling for a final inspection.
|
1st review completed | | | 6/14/2010 | | DONE |
|
|
|
|
Alarm Plan Check | 6/14/2010 | | 6/14/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
Approved. A plan modification will be required to be submitted and approved prior to calling for final inspection.
|
PLANS TAKEN FRONT DESK ALARM | | | 6/14/2010 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Inspection Record Card- Fire | 6/14/2010 | | 6/14/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 6/14/2010 | | DONE |
|
|
|
t/c w phil at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 6/14/2010 | | DONE |
|
|
|
|
Telephone call | | | 6/9/2010 | | DONE |
|
|
|
Spoke to Rob to let him know there is a stamped engineered set of fire alarm plans in the building plans, therefore they are to be the engineer of record. I let him know I need a letter from the engineer indicating they have reviewed the plans. The designer listed on the permit application will be changed from Rob Ahten to the designer from CSHQA.
|
Application received | | | 6/7/2010 | | |
|
|
|
|