Miscellaneous action | | | 7/28/2010 | | DONE |
|
|
|
FA plans taken to records for scanning.
|
INSP-Final Inspection | 7/15/2010 | 7/15/2010 | 7/15/2010 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. A supervisory point has been added.
|
INSP-Final Inspection | 7/6/2010 | 7/7/2010 | 7/7/2010 | P | FAIL |
Troy Cobbley
|
|
|
The netcon was a 5. The alarm and trouble signals tested ok. No supervisory signal was being separately transmitted but was instead transmitting out under the trouble contacts. Per Sean Stone, at SimplexGrinnell, this Autocall panel is capable of providing an individual supervisory signal with an additional relay. Since this panel is capable of this a separate supervisory signal is required.
|
Issue and Print Permit | | | 6/28/2010 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 6/18/2010 | | 6/24/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
6/24/2010 10:48:50 SLC - activity updated through activity FIRA24 from case FIR10-00288.
|
1st review completed | | | 6/24/2010 | | DONE |
|
|
|
|
Alarm Plan Check | 6/24/2010 | | 6/24/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
approved
|
PLANS TAKEN FRONT DESK ALARM | | | 6/24/2010 | | DONE |
|
|
|
Approved plans available at front counter
|
Inspection Record Card- Fire | 6/24/2010 | | 6/24/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 6/24/2010 | | DONE |
|
|
|
t/c w lori at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 6/24/2010 | | DONE |
|
|
|
|
Application received | | | 6/18/2010 | | |
|
|
|
|