Miscellaneous action | | | 8/13/2010 | | DONE |
|
|
|
FA plans taken to records for scanning
|
INSP-Final Inspection | 8/6/2010 | 8/6/2010 | 8/6/2010 | P | PASS |
Forrest France
|
|
|
Re-inspection for correction items passed, dry system pressure switch reset repaired by sprinkler contractor, fire alarm permit final okayed.
|
INSP-Final Inspection | 8/3/2010 | 8/4/2010 | 8/5/2010 | P | FAIL |
Forrest France
|
|
|
Notes for inspection completed 8/4 include; provide lock at the breaker to the panel, map at panel, signage at the door to the FACP room, correct address for FS and TS points at the 2nd and 3rd floor, tamper switch at the 4th floor dry system initiated a general alarm condition, missing TS point on the plans and matrix for the elevator control valve at the penthouse, incorrect cd ratings at the penthouse and 4th floor lobby repaired while on site.
|
INSP-Final Inspection | 7/29/2010 | 8/3/2010 | 8/3/2010 | A | FAIL |
Forrest France
|
|
|
See plan set for annotations regarding locations of correction items including cd ratings at several areas, SD placement, MP height, duct detector housings at exterior locations, trouble on the panel, item 6 on plan review comments, etc.
|
Miscellaneous action | | | 7/26/2010 | | DONE |
|
|
|
Recieved as-builts for changes made to the first floor. No plan modification or resubmittals required.
|
INSP-Alarm Testing | 7/22/2010 | 7/22/2010 | 7/22/2010 | P | NR |
Forrest France
|
|
|
|
Issue and Print Permit | | | 6/30/2010 | | DONE |
|
|
|
|
Telephone call | | | 6/29/2010 | | DONE |
|
|
|
Spoke to Rob and let him know I need a new letter from the engineer stating they have reviewed the changes indicated in the resubmittal drawings.
|
Alarm Plan Check | 6/29/2010 | | 6/29/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
see redlines and review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 6/29/2010 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Inspection Record Card- Fire | 6/29/2010 | | 6/29/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 6/29/2010 | | DONE |
|
|
|
t/c w tyler at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 6/29/2010 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 6/21/2010 | | 6/29/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
6/29/2010 15:46:17 SLC - activity updated through activity FIRA24 from case FIR10-00290.
|
Plan assigned to (Stephanie) | 6/21/2010 | | 6/29/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
6/29/2010 15:46:17 SLC - activity updated through activity FIRA24 from case FIR10-00290.
|
1st review completed | | | 6/25/2010 | | DONE |
|
|
|
|
Alarm Plan Check | 6/25/2010 | | 6/25/2010 | | FAIL |
Stephanie L. Cobbley
|
|
|
see redlines
|
Telephone call | | | 6/25/2010 | | DONE |
|
|
|
Spoke to Rob to let him know the plans would need to be rejected. He asked if he could call me back when he gets to his office and has the plans in front of him to go over the deficiencies.
|
Telephone call | | | 6/25/2010 | | DONE |
|
|
|
Went over the deficiencies on the phone with Rob.
|
Miscellaneous action | | | 6/25/2010 | | DONE |
|
|
|
Faxed review comments to the applicant
|
Miscellaneous action | | | 6/25/2010 | | DONE |
|
|
|
denied plans available at front counter for customer pick up.
|
Application received | | | 6/21/2010 | | |
|
|
|
|