Permit Information
Permit NumberFIR10-00290
StatusFinaled
Name R M E INC
Site Address 805 W IDAHO ST
Project NameBOISE CITY NATL BANK BLDG
Customer Number 
ePlanReview 
Description
This fire alarm permit is to replace the existing fire alarm panel, notification devices, as well as most of the initiating devices. The core/shell areas and the first floor tenant devices are to be placed in order to meet current IFC and NFPA 72 requirements. Devices included in this permit scope are monitor modules for sprinkler system monitoring, HVAC shutdown, a pull station, connection for the kitchen hood, notification throughout the first floor tenant, notification in the core areas (central corridors and public restrooms) for the basement through the penthouse. All notification devices are being replaced and are to meet NFPA 72 mounting and spacing requirements. Some of the existing initiating devices are to remain but will be monitored with new addressable monitor modules. The elevator upgrade devices are covered in FIR10-00293. Tenants other than the first floor will require separate fire alarm permits.

Associated building permit: BLD10-00831 (BOISE CITY NATIONAL BANK BUILDING - CORE REMODEL) The fire sprinkler system substitutes for the 1-hr fire-resistance-rating of the building structure. To remodel the core areas within an existing 5 story building (basement, 4 stories above grade plane, and enclosed mezzanine above the 4th story). Work is to include an interior non-fire-resistance-rated exit discharge on the ground floor to serve an existing stairway enclosure, a non-fire-resistance-rated corridor on the 2nd story to connect stairway enclosures, new suspended ceilings within some core areas, and new finishes in existing restrooms. Two new doorways will be created in existing masonry walls. Steel headers and trimmers will be provided. Common restrooms on the 1st story, 2nd story, 3rd story, and 4th story are required to be accessible to the disabled as defined by current standards, unless technically infeasible. Upgrades will be done where necessary to ensure compliance to the maximum extent possible. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. Some of the trade-offs permitted because this building is fully fire sprinklered are (1) egress from an enclosed stairway is allowed through an interior non-fire-resistance-rated lobby on the ground floor and (2) non-fire-resistance-rated corridors are allowed on all levels. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. Existing fire sprinkler heads will be replaced with quick-response sprinklers in the future on a floor by floor basis as allowed by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  8/13/2010 DONE
FA plans taken to records for scanning
INSP-Final Inspection8/6/20108/6/20108/6/2010PPASS
DetailsForrest France
Re-inspection for correction items passed, dry system pressure switch reset repaired by sprinkler contractor, fire alarm permit final okayed.
INSP-Final Inspection8/3/20108/4/20108/5/2010PFAIL
DetailsForrest France
Notes for inspection completed 8/4 include; provide lock at the breaker to the panel, map at panel, signage at the door to the FACP room, correct address for FS and TS points at the 2nd and 3rd floor, tamper switch at the 4th floor dry system initiated a general alarm condition, missing TS point on the plans and matrix for the elevator control valve at the penthouse, incorrect cd ratings at the penthouse and 4th floor lobby repaired while on site.
INSP-Final Inspection7/29/20108/3/20108/3/2010AFAIL
DetailsForrest France
See plan set for annotations regarding locations of correction items including cd ratings at several areas, SD placement, MP height, duct detector housings at exterior locations, trouble on the panel, item 6 on plan review comments, etc.
Miscellaneous action  7/26/2010 DONE
Recieved as-builts for changes made to the first floor. No plan modification or resubmittals required.
INSP-Alarm Testing7/22/20107/22/20107/22/2010PNR
DetailsForrest France
Issue and Print Permit  6/30/2010 DONE
Telephone call  6/29/2010 DONE
Spoke to Rob and let him know I need a new letter from the engineer stating they have reviewed the changes indicated in the resubmittal drawings.
Alarm Plan Check6/29/2010 6/29/2010 PASS
DetailsStephanie L. Cobbley
see redlines and review comments
PLANS TAKEN FRONT DESK ALARM  6/29/2010 DONE
Approved redlined plans available at front counter
Inspection Record Card- Fire6/29/2010 6/29/2010 DONE
DetailsPatricia Smith
Telephone call  6/29/2010 DONE
t/c w tyler at ###-#### - permit ready and fees given
Permit Ready to Issue  6/29/2010 DONE
Details
Plan assigned to (Stephanie)6/21/2010 6/29/2010 DONE
DetailsStephanie L. Cobbley
6/29/2010 15:46:17 SLC - activity updated through activity FIRA24 from case FIR10-00290.
Plan assigned to (Stephanie)6/21/2010 6/29/2010 DONE
DetailsStephanie L. Cobbley
6/29/2010 15:46:17 SLC - activity updated through activity FIRA24 from case FIR10-00290.
1st review completed  6/25/2010 DONE
Alarm Plan Check6/25/2010 6/25/2010 FAIL
DetailsStephanie L. Cobbley
see redlines
Telephone call  6/25/2010 DONE
Spoke to Rob to let him know the plans would need to be rejected. He asked if he could call me back when he gets to his office and has the plans in front of him to go over the deficiencies.
Telephone call  6/25/2010 DONE
Went over the deficiencies on the phone with Rob.
Miscellaneous action  6/25/2010 DONE
Faxed review comments to the applicant
Miscellaneous action  6/25/2010 DONE
denied plans available at front counter for customer pick up.
Application received  6/21/2010