Miscellaneous action | | | 6/8/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 2/8/2011 | 2/9/2011 | 2/9/2011 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
INSP-Final Inspection | 2/4/2011 | 2/4/2011 | 2/4/2011 | P | FAIL |
Forrest France
|
|
|
Noted items include; non-functional outside bell, missing escutcheons, secure control valves, signage/calc. info at riser, provide data sheets for exposed supply pipe, pendent head at one room appears obstructed per NFPA 13D 8.2.5.2.1.
|
Telephone call | | | 1/27/2011 | | DONE |
|
|
|
Spoke with Cam at Shilo
Told him he had to resubmit a new drawing for the underground since his previous drawing excluded the underground. I told him Shilo would be responsible for the underground regardless of whom may have actually installed the underground because the permit will be in there name. I also told him that there would be a double fee required since the underground was installed without a permit. I told him only a licensed fire protection contractor could install the underground since it was a dedicated fire protection line.
|
Telephone call | | | 1/27/2011 | | DONE |
|
|
|
Spoke with Cam at Shilo.
He said the builder is going to use the original design which is a combination domestic and fire protection service. There will be no dedicate fire protection service at this time.
|
INSP-Conference | 12/9/2010 | 12/10/2010 | 12/10/2010 | A | DONE |
Troy Cobbley
|
|
|
I met with Mark from Shilo and we discussed the underground supply line being buried with out any inspections. I left a correction notice referencing IFC 106.2 and 106.3
|
INSP-Sprinkler Rough-in | 7/19/2010 | 7/19/2010 | 7/19/2010 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping in the master bedroom can be covered. I discussed with Richard the requirement for me to verify underground supply piping bury depth and flushing prior to cover.
|
INSP-Sprinkler Rough-in | 7/16/2010 | 7/16/2010 | 7/16/2010 | P | PART |
Troy Cobbley
|
|
|
The fire sprinkler piping is ok to cover except in the southwest/master bedroom, there are tenting issues here. I went over possible sprinkler pendant obstruction issues with the builder.
|
INSP-Sprinkler Rough-in | 7/12/2010 | 7/16/2010 | 7/16/2010 | A | FAIL |
Troy Cobbley
|
|
|
No responce from the phone contact 30 min. prior to arriving on site. Once on site I met the builder but no city approved plans were on site for the inspection. The builder was already starting to cover the un-inspected fire sprinkler piping so I stopped that and request that the installed sheet rock be removed. I also pointed out tenting and insulation that was not installed correctly.
|
INSP-Sprinkler Rough-in | 7/12/2010 | 7/13/2010 | 7/12/2010 | P | CANC |
Troy Cobbley
|
|
|
later afternoon would be best if possible. Richard is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
Issue and Print Permit | | | 7/12/2010 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 6/29/2010 | | 7/8/2010 | | DONE |
Tim Frost
|
|
|
7/8/2010 14:23:52 TRF - activity updated through activity FIRA22 from case FIR10-00300.
|
Sprinkler Plan Check | 7/8/2010 | | 7/8/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/8/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 7/8/2010 | | 7/8/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 7/8/2010 | | DONE |
|
|
|
left vm for cameron at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/8/2010 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/7/2010 | | 7/7/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 7/7/2010 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 7/7/2010 | | DONE |
|
|
|
Emailed review to contractor.
|
Telephone call | | | 7/7/2010 | | DONE |
|
|
|
t/c w cameron at ###-#### - permit denied - needs to be picked up and resubmitted
|
Plan resubmittals received | | | 7/7/2010 | | DONE |
|
|
|
received 3 sets of plans / applications sent to Tim Frost
|
Telephone call | | | 7/2/2010 | | DONE |
|
|
|
Shiloh requested an early start.
|
Early Start | | | 7/2/2010 | | DONE |
Scott Arellano
|
|
|
Request approved under the conditions stipulated in the approval document.
|
Application received | | | 6/29/2010 | | |
|
|
|
|