Miscellaneous action | | | 12/21/2010 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 12/17/2010 | 12/17/2010 | 12/17/2010 | P | PASS |
Forrest France
|
|
|
Fire alarm permit finaled.
|
FIR-Aging Inspection | 11/22/2010 | 11/22/2010 | 11/22/2010 | | DONE |
Forrest France
|
|
|
Pending related fire sprinkler work.
|
FIR-Aging Inspection | 9/22/2010 | 9/22/2010 | 9/22/2010 | P | PART |
Forrest France
|
|
|
Final pending fire sprinkler permit activity.
|
INSP-Final Inspection | 8/17/2010 | 8/17/2010 | 8/17/2010 | P | PART |
Forrest France
|
|
|
Temporary occupancy approval okayed per M. Senteno.
|
INSP-Final Inspection | 8/13/2010 | 8/16/2010 | 8/16/2010 | A | PART |
Forrest France
|
|
|
Remainder of fire alarm work tested satisfactory, correction items finished. Permit final pending outside control valve/tamper switch arrangement at the fire sprinkler system riser which may require modification.
|
INSP-Final Inspection | 8/10/2010 | 8/11/2010 | 8/11/2010 | P | PART |
Forrest France
|
|
|
Fire alarm acceptance testing completed satisfactory with the exception of duct smoke detection devices due to installation locations in need of revision.
|
Plan assigned to (Stephanie) | 7/8/2010 | | 7/21/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
7/21/2010 10:43:02 SLC - activity updated through activity FIRA24 from case FIR10-00319.
|
Alarm Plan Check | 7/21/2010 | | 7/21/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved - see redlines and review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 7/21/2010 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Inspection Record Card- Fire | 7/21/2010 | | 7/21/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 7/21/2010 | | DONE |
|
|
|
left message for bret at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/21/2010 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/21/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/15/2010 | | DONE |
|
|
|
received application and two copies of submittal folder and plans; taken to Fire Review.
|
1st review completed | | | 7/14/2010 | | DONE |
|
|
|
|
Alarm Plan Check | 7/14/2010 | | 7/14/2010 | | FAIL |
Stephanie L. Cobbley
|
|
|
Plans denied - see redlined plans and review comments
|
Telephone call | | | 7/14/2010 | | DONE |
|
|
|
Spoke to Bret regarding the plan discrepencies and let him know the plans are being denied.
|
Miscellaneous action | | | 7/14/2010 | | DONE |
|
|
|
Faxed review comments to Mountain Alarm
|
Miscellaneous action | | | 7/14/2010 | | DONE |
|
|
|
redlined denied plans taken up to permit desk for contractor pick up.
|
Miscellaneous action | | | 7/14/2010 | | DONE |
Tisha Gallop
|
|
|
picked up failed plans
|
Application received | | | 7/8/2010 | | |
|
|
|
|