Miscellaneous action | | | 1/14/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 12/6/2010 | 12/7/2010 | 12/7/2010 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
FIR-Aging Inspection | 12/3/2010 | 12/3/2010 | 12/7/2010 | | PASS |
Troy Cobbley
|
|
|
|
INSP-Sprinkler Rough-in | 8/5/2010 | 8/6/2010 | 8/6/2010 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 8/5/2010 | 8/6/2010 | 8/6/2010 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in | 8/3/2010 | 8/4/2010 | 8/4/2010 | P | PASS |
Troy Cobbley
|
|
|
All of the sprinkler piping is complete and can be covered except for the 1 1/4" main has not been installed or the new pendant head in front of the doorway.
|
Plan assigned to (Tim) | 7/8/2010 | | 7/19/2010 | | DONE |
Tim Frost
|
|
|
7/19/2010 11:29:37 TRF - activity updated through activity FIRA22 from case FIR10-00321.
|
Telephone call | | | 7/19/2010 | | DONE |
|
|
|
Talked with John and asked him to send me the rest of the peaking information for the hydraulic calculations.
On hold waiting for the information.
|
Sprinkler Plan Check | 7/19/2010 | | 7/19/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/19/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 7/19/2010 | | 7/19/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 7/19/2010 | | DONE |
|
|
|
t/c w randy at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/19/2010 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/19/2010 | | DONE |
|
|
|
|
Telephone call | | | 7/19/2010 | | DONE |
|
|
|
The fire protection scope of work has been changed. The riser and backflow preventer are to remain as is. The backflow is apparently 4" and the riser is 3". The drawings were changed in the second submittal and not ballooned. The plan reviewer therefore did not notice the change.
|
Plan resubmittals received | | | 7/15/2010 | | DONE |
Tisha Gallop
|
|
|
received three copies of application, submittal documents and plans; taken to fire review
|
Telephone call | | | 7/14/2010 | | DONE |
Barbara Stitt
|
|
|
Left message that plans were denied on 7-14-10 @ 8:00am BAS
|
Sprinkler Plan Check | 7/13/2010 | | 7/13/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 7/13/2010 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 7/13/2010 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Application received | | | 7/8/2010 | | |
|
|
|
|
Pending Assignment by SAM | 7/8/2010 | | 7/8/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
7/8/2010 16:49:54 ALR - activity updated through activity FIRA158 from case FIR10-00321.
|