Miscellaneous action | | | 9/8/2010 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 8/26/2010 | 8/26/2010 | 8/26/2010 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 8/25/2010 | 8/25/2010 | 8/25/2010 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled for tomorrow when the fire alarm contractor is ready.
|
INSP-Sprinkler Rough-in/Hydro | 8/18/2010 | 8/18/2010 | 8/18/2010 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro test passed and the remaining sprinkler piping can be covered. One earthquake bracing was not installed but was installed by the end of the hydro test.
|
INSP-Sprinkler Rough-in | 8/16/2010 | 8/17/2010 | 8/17/2010 | A | PART |
Forrest France
|
|
|
Seismic bracing inspection passed- okay to replace insulation at the truss members.
|
INSP-Sprinkler Rough-in | 7/29/2010 | 7/30/2010 | 7/30/2010 | A | PASS |
Troy Cobbley
|
|
|
The front lobby hardlid area piping is ok to cover. The earthquaking needs addressed. The earthquake detail were not legible. Clearer details need to be provided at the next inspection.
|
Issue and Print Permit | | | 7/19/2010 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 7/9/2010 | | 7/16/2010 | | DONE |
Tim Frost
|
|
|
7/16/2010 11:51:15 TRF - activity updated through activity FIRA22 from case FIR10-00322.
|
Sprinkler Plan Check | 7/16/2010 | | 7/16/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/16/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 7/16/2010 | | 7/16/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 7/16/2010 | | DONE |
|
|
|
left vm for shaun at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/16/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/14/2010 | | DONE |
Tisha Gallop
|
|
|
received three copies of application, submittal documents and plans; taken to Fire Review.
|
Sprinkler Plan Check | 7/12/2010 | | 7/12/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 7/12/2010 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 7/12/2010 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Telephone call | | | 7/12/2010 | | DONE |
|
|
|
t/c w shaun at ###-#### - permit denied - needs to be picked up and resubmitted
|
Application received | | | 7/9/2010 | | |
|
|
|
|
Pending Assignment by SAM | 7/9/2010 | | 7/9/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
7/9/2010 08:15:21 ALR - activity updated through activity FIRA158 from case FIR10-00322.
|