Permit Information
Permit NumberFIR10-00322
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 7940 W RIFLEMAN ST Unit: 140
Project NameFidelity Investments
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of providing a new system for the east portion (east of column line F) of the building. The building was sprinklered with above protection in 11-06 as shell and core. The work under this permit is for the pendent sprinklers in the new ceiling. A new 3" wet riser is being cut into the existing 6" header. The existing header is supplied from 6" underground and 6" backflow preventer. All new sprinklers are to be quick response.

(Fidelity Investments) Permit for tenant improvements to an existing 4,150 sq. ft. tenant space with work to include two new accessible restrooms, construction of new interior non-bearing partition walls, Suspended ceiling, new vestibule, HVAC ducting, fire sprinkler, electrical and all related interior finishes. All work to be done per the approved plans, plan review report and any notations. This is a fully sprinklered building; any alterations to the existing sprinkler system will require a separate permit and shall comply with NFPA 13 as regulated by the City of Boise fire department. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  9/8/2010 DONE
Sent to records for scanning.
INSP-Final Inspection8/26/20108/26/20108/26/2010PPASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection8/25/20108/25/20108/25/2010PCANC
DetailsTroy Cobbley
To be rescheduled for tomorrow when the fire alarm contractor is ready.
INSP-Sprinkler Rough-in/Hydro8/18/20108/18/20108/18/2010PPASS
DetailsTroy Cobbley
The overhead hydro test passed and the remaining sprinkler piping can be covered. One earthquake bracing was not installed but was installed by the end of the hydro test.
INSP-Sprinkler Rough-in8/16/20108/17/20108/17/2010APART
DetailsForrest France
Seismic bracing inspection passed- okay to replace insulation at the truss members.
INSP-Sprinkler Rough-in7/29/20107/30/20107/30/2010APASS
DetailsTroy Cobbley
The front lobby hardlid area piping is ok to cover. The earthquaking needs addressed. The earthquake detail were not legible. Clearer details need to be provided at the next inspection.
Issue and Print Permit  7/19/2010 DONE
Plan assigned to (Tim)7/9/2010 7/16/2010 DONE
DetailsTim Frost
7/16/2010 11:51:15 TRF - activity updated through activity FIRA22 from case FIR10-00322.
Sprinkler Plan Check7/16/2010 7/16/2010 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  7/16/2010 DONE
DetailsTim Frost
Inspection Record Card- Fire7/16/2010 7/16/2010 DONE
DetailsPatricia Smith
Telephone call  7/16/2010 DONE
left vm for shaun at ###-#### - permit ready and fees given
Permit Ready to Issue  7/16/2010 DONE
Details
Plan resubmittals received  7/14/2010 DONE
DetailsTisha Gallop
received three copies of application, submittal documents and plans; taken to Fire Review.
Sprinkler Plan Check7/12/2010 7/12/2010 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  7/12/2010 DONE
DetailsTim Frost
Miscellaneous action  7/12/2010 DONE
DetailsTim Frost
Emailed review to contractor
Telephone call  7/12/2010 DONE
t/c w shaun at ###-#### - permit denied - needs to be picked up and resubmitted
Application received  7/9/2010  
Pending Assignment by SAM7/9/2010 7/9/2010 DONE
DetailsAlexandra L. DeYoung
7/9/2010 08:15:21 ALR - activity updated through activity FIRA158 from case FIR10-00322.