Miscellaneous action | | | 10/26/2010 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 9/16/2010 | 9/17/2010 | 9/16/2010 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 9/14/2010 | 9/14/2010 | 9/14/2010 | P | PART |
Forrest France
|
|
|
Pending project related fire alarm permit work.
|
INSP-Final Inspection | 9/13/2010 | 9/13/2010 | 9/13/2010 | P | PART |
Forrest France
|
|
|
Final pending control valve supervision at the spray booth.
|
INSP-Final Inspection | 9/9/2010 | 9/10/2010 | 9/10/2010 | A | FAIL |
Forrest France
|
|
|
SW head at the exterior compressor room appears painted, provide bags at pendent heads in the spray booth per NFPA 13, upright heads within the 7' zone of the unit heaters must be high temperature per fig.8.3.2.5, control valve at supply to booth heads needs to be supervised.
|
INSP-Sprinkler Rough-in | 7/26/2010 | 7/26/2010 | 7/26/2010 | P | PART |
Forrest France
|
|
|
Rough-in with the exception of piping at the spray booth not yet installed is satisfactory. SW head to be provided at the overhead door.
|
Issue and Print Permit | | | 7/26/2010 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 7/14/2010 | | 7/23/2010 | | DONE |
Tim Frost
|
|
|
7/23/2010 10:03:45 TRF - activity updated through activity FIRA22 from case FIR10-00338.
|
Sprinkler Plan Check | 7/23/2010 | | 7/23/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/23/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 7/23/2010 | | 7/23/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 7/23/2010 | | DONE |
|
|
|
t/c w don at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/23/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/21/2010 | | DONE |
Tisha Gallop
|
|
|
received three copies of application, submittal documents and plans; routed to Fire Review
|
Sprinkler Plan Check | 7/16/2010 | | 7/16/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 7/16/2010 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 7/16/2010 | | DONE |
|
|
|
t/c w don at ###-#### - permit denied - needs to be picked up and resubmitted
|
Miscellaneous action | | | 7/15/2010 | | DONE |
|
|
|
Sent an email to the contractor as follows:
I will need a completed and signed owner's certificate for this project per the City of Boise checklist. In addition, I need to know exactly what is being stored and how it is package. The height of the storage and aisle widths (if applicable.)
The review will be on hold pending the above information.
|
Application received | | | 7/14/2010 | | |
|
|
|
|