Permit Information
Permit NumberFIR10-00339
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 11665 W THOMAS DR
Project NameWinston H. Moore Addition
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of a voluntary residential 13D sprinkler system. The extended coverage sprinklers are based on 20'x20' spacing. The piping will be installed tented in the attic. The system is supplied by well pump capable of supplying 40 Gpm @ 60 Psi for in the excess of 7 minutes required by NFPA 13D

Permit for a addition of 1,809 sq. ft. to an existing single family dwelling with work to include: excavation, concrete, grading, framing and all related interior and exterior finishes. Separate electrical, plumbing and mechanical permits are required. All work to be done per the approved plans. A-1 zoning and setbacks per planning.

Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  1/14/2011 DONE
Sent to records for scanning.
INSP-Final Inspection11/19/201011/19/201011/19/2010PPASS
DetailsTroy Cobbley
permit finaled
CHANGE STATUS TO (ISS)  11/19/2010 DONE
changed to issue status per trf
Miscellaneous action  11/16/2010 DONE
Received as built drawings. The only change was, changing the sprinklers in the two bedrooms to Tyco LFII. This was necessitated due to information regarding where the pump was set to only produce 40 GPM.
Plan resubmittals received  11/12/2010 DONE
DetailsTisha Gallop
Plan Modification: Received three copies of application, submittal documents and plans; routed to fire review.
INSP-Final Inspection11/8/201011/8/201011/8/2010PFAIL
DetailsTroy Cobbley
The testing of the bell passed. We are now waiting on a letter from the pump provider verifying that the correct gpm and psi has been provided. The letter will be sent to Tim Frost for verification prior to setting up another final inspection.
INSP-Final Inspection11/1/201011/2/201011/2/2010AFAIL
DetailsTroy Cobbley
The inspector's test has not been set up to verify note "B" of the review comments. (two heads for 7 minutes). All other items appear ok.
INSP-Final Inspection11/1/201011/1/201011/1/2010PCANC
DetailsTroy Cobbley
Lonnie and my schedules did not meet. Rescheduled for tomorrow.
INSP-Sprinkler Rough-in8/31/20109/1/20109/1/2010APASS
DetailsTroy Cobbley
The added pendants/piping, due to ceiling obstructions, is ok for cover.
INSP-Sprinkler Rough-in8/26/20108/26/20108/26/2010PPASS
DetailsTroy Cobbley
Sprinkler piping is ok to cover. Per Lonnie and I's conversation, 8" lintels will be installed at the shower/soffit to avoid instlling sprinkler pendants in the showers.
Issue and Print Permit  7/19/2010 DONE
Plan assigned to (Tim)7/14/2010 7/16/2010 DONE
DetailsTim Frost
7/16/2010 13:35:13 TRF - activity updated through activity FIRA22 from case FIR10-00339.
Sprinkler Plan Check7/16/2010 7/16/2010 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  7/16/2010 DONE
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  7/16/2010 DONE
DetailsTim Frost
Inspection Record Card- Fire7/16/2010 7/16/2010 DONE
DetailsPatricia Smith
Telephone call  7/16/2010 DONE
left vm for jeff at ###-#### - permit ready and fees given
Permit Ready to Issue  7/16/2010 DONE
Details
Miscellaneous action  7/15/2010 DONE
Spoke to the contractor and asked him to provided documentation that well can supply the 40 Gpm @ 60 Psi for 7 minutes.

The project is on hold until the documentation is supplied.
Application received  7/14/2010  
Pending Assignment by SAM7/14/2010 7/14/2010 DONE
DetailsAlexandra L. DeYoung
7/14/2010 16:21:13 ALR - activity updated through activity FIRA158 from case FIR10-00339.