Miscellaneous action | | | 2/9/2011 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 1/21/2011 | 1/21/2011 | 1/21/2011 | P | PASS |
Forrest France
|
|
|
Inspection notes 1/21/11- Flow switch repaired and retested okay. Audible notification adjustments okayed. Fire alarm permit final approved.
|
INSP-Final Inspection | 1/20/2011 | 1/20/2011 | 1/21/2011 | P | PART |
Forrest France
|
|
|
Inspection notes 1/20/11- Completed acceptance testing including initiating and notification devices, sprinkler monitoring, and elevator control functions. Verified offsite monitoring. Flashing hat at the elevator is not required due to original installation date of the equipment per plan review. Flow switch at the wet system riser did not pass operational testing. Remainder of items tested okay.
|
INSP-Final Inspection | 1/18/2011 | 1/19/2011 | 1/21/2011 | A | PART |
Forrest France
|
|
|
Inspection notes 1/19/11- Completed project walkthrough- noted some locations where audibility may be insufficient, cd rating at the second floor breakroom adjusted, one DD is supply side located, "shadowed" areas to be verified during functional testing. Verified as-builts per request.
|
Alarm Plan Check | 1/14/2011 | | 1/14/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Plan modification approved with redlines and review comments. As-builts shall be required at time of inspection.
|
PLANS TAKEN FRONT DESK ALARM | | | 1/14/2011 | | DONE |
|
|
|
approved redlined plans available at front counter
|
Inspection Record Card- Fire | 1/14/2011 | | 1/14/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 1/14/2011 | | DONE |
|
|
|
t/c w larry - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 1/14/2011 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 1/14/2011 | | DONE |
Christina Prado
|
|
|
Plans picked up 1-14-11
|
Plan resubmittals received | | | 1/3/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
Received two copies of application, Information packets and plans E141-E143, FACP, NAC, NDL and site plan
|
INSP-Conference | 12/21/2010 | 12/22/2010 | 12/22/2010 | A | DONE |
Forrest France
|
|
|
Regarding field modifications and plan resubmital.
|
FIR-Aging Inspection | 11/12/2010 | 11/12/2010 | 11/12/2010 | | DONE |
Forrest France
|
|
|
Site work in progress, construction underway.
|
INSP-Conference | 8/31/2010 | 8/31/2010 | 9/1/2010 | P | DONE |
Forrest France
|
|
|
Regarding notification appliance locations with respect to equipment layout at one area.
|
Issue and Print Permit | | | 8/24/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (Stephanie) | 8/12/2010 | | 8/20/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
8/20/2010 09:19:51 SLC - activity updated through activity FIRA24 from case FIR10-00398.
|
Telephone call | | | 8/20/2010 | | DONE |
|
|
|
John with CH2MHILL called to answer the questions I had and clarify discrepencies in the plans. I asked him to email with what we'd discussed over the phone. I recieved that email a short time later.
|
1st review completed | | | 8/20/2010 | | DONE |
|
|
|
|
Alarm Plan Check | 8/20/2010 | | 8/20/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
Approved with redlines
|
PLANS TAKEN FRONT DESK ALARM | | | 8/20/2010 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Inspection Record Card- Fire | 8/20/2010 | | 8/20/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 8/20/2010 | | DONE |
|
|
|
left vm for larry at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 8/20/2010 | | DONE |
|
|
|
|
Telephone call | | | 8/19/2010 | | DONE |
|
|
|
Spoke to Rick at NWS to go over some areas of the plans that I needed clarification on. He was able to answer some of my questions, and for the other clarifications he let me know I would need to call the engineer.
|
Telephone call | | | 8/19/2010 | | DONE |
|
|
|
Left a message of John Hatten at CH2MHILL letting him know I have questions on the fire alarm plans.
|
Application received | | | 8/12/2010 | | |
|
|
|
|