Permit Information
Permit NumberFIR10-00400
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 5656 W MORRIS HILL RD
Project NameStein Warehouse
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of adding fire protection to three existing buildings that are joined together to form one facility. There is no associated building permit at this time. There will be two gridded systems for high pile storage and one system for the offices and storage rooms below a mezzanine. The systems will be supplied through new 6” Udg and backflow preventer. The system is designed for Class I storage. The commodity is beer in glass and cans in cardboard boxes.

Plan Mod Scope:

Numerous revisions required due to field inspector final inspection. Changes included - main sizes, additional fittings, end sprinkler spacing, revised hydraulics, new hydraulics, upright protection added in combustible concealed area and combustible concealed spaces filled with non-combustible insulation. This review is for plan mod changes only.

________________________________________

Fire Protection Contractor Notice:

The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. These changes may affect the sprinkler system. The sprinkler contractor will be required to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit they will do so on their own cognizance.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Plan assigned to (Tim)11/5/2010 2/6/2012 DONE
DetailsTim Frost
Plan assigned to (Tim)11/9/2010 2/6/2012 DONE
DetailsTim Frost
Miscellaneous action  1/14/2011 DONE
Sent to records for scanning.
INSP-Final Inspection11/12/201011/15/201011/15/2010APASS
DetailsTroy Cobbley
Permit finaled. Bill to provide test papers and sticker on outside alarm bell as discussed for tomorrows life safety inspection.
INSP-Sprinkler Rough-in/Hydro11/12/201011/15/201011/15/2010APASS
DetailsTroy Cobbley
The remaining overhead hydro tests passed.
INSP-Final Inspection11/12/201011/12/201011/12/2010PCANC
DetailsTroy Cobbley
Project is not ready for a final inspection. See corrections required entered under the rough-in sprinkler inspection request.
INSP-Sprinkler Rough-in/Hydro11/12/201011/12/201011/12/2010PFAIL
DetailsTroy Cobbley
Forrest France worked Thursday 11/11/10 to perform hydro tests on the new sprinkler systems. This inspection has not been logged in under a separate inspection due to the plan status being in the Rev status due to an additional resubmittal for plan modifications. Forrest found that systems #1, #2 and #3 had been pumped up but the system header and FDC piping had not. The fitter stated that these items would be tested the following day. Forrest started the two hour testing and upon his return found that a mechanical tee had failed under pressure on system #2. So on 11/11/10 systems #1 and #3 passed hydro.


Todays (11/12/10) hydro test was for the header and FDC piping. System #2 had not been set back up for testing. After starting the hydro testing Bill and I started the inspection to verify the corrected items on the latest plan modifications. Everything was completed except 14 sprinkler heads along the south wall did not get relocated as required on the plan modifications and two upright heads were still exceeding their half spacing in the upper level Storage Room. So a total of 16 sprinkler heads needed to be relocated. The other correction items including the installation of insulation in the joist channels had been completed. Due to the 16 heads needing relocated, the sprinkler systems where these heads are located, will need to be re-hydro tested. At this point it was agreed to end the header and FDC hydro test and go ahead and perform the forward flow verification for the backflow preventor which passed easily out of a single 2 1/2" outlet. In conclusion to finish this sprinkler permit, the 16 relocated heads need to be finished, hydro testing performed and the verification of fire alarm interconnections.
CHANGE STATUS TO (ISS)  11/12/2010 DONE
DetailsBarbara Stitt
(F) Reprint permit  11/12/2010 DONE
DetailsBarbara Stitt
Inspection Record Card- Fire11/12/2010 11/12/2010 DONE
DetailsBarbara Stitt
Sprinkler Plan Check11/10/2010 11/10/2010 PASS
DetailsTim Frost
Plan resubmittals received  11/9/2010  
DetailsBarbara Stitt
Sprinkler Plan Check11/8/2010 11/8/2010 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  11/8/2010 DONE
DetailsTim Frost
Meeting  11/8/2010 DONE
Meeting with Randy Boron to discussed changes required for the plan mod. Explained in detail that the plans, hydraulics, seismic calculations must ALL match.
Telephone call  11/5/2010 DONE
Called Randy Bowron and told him that I was denying the plan. The hydraulic calculations did not match the actual installation and there were density issues in remote area 5.
Plan resubmittals received  11/5/2010  
DetailsBarbara Stitt
INSP-Final Inspection11/3/201011/4/201011/4/2010PFAIL
DetailsTroy Cobbley
Todays inspection was actually just an underground flush which passed inspection. This project is not ready for a final inspection at this time. See previous correction items noted.
INSP-Sprinkler Rough-in11/2/201011/3/201011/3/2010PFAIL
DetailsTroy Cobbley
Plans need to be resubmitted showing all piping changes and additional sprinkler heads. Revised hydraulic calculations are required showing the routing changes and additional fitting added due to structural members. Resubmittals were required per the approved plans if additional fittings or piping were provided. See the city approved plans for locations of deficiencies as marked in red. Two items not marked on the plans but discussed with Bill were the clearance for the main penatrations through the block walls and a letter from a structural engineer or manufacturer addressing/approving the drilling of the structural members to mount the siesmic bracing.
INSP-Sprinkler Rough-in/Hydro11/2/201011/3/201011/3/2010PFAIL
DetailsTroy Cobbley
Duplicate inspection for a hydro. See previous notes.
INSP-Supply line flush11/2/201011/3/201011/3/2010APART
DetailsTroy Cobbley
The underground hydro test passed. Could not perform above ground hydro tests or flush the underground supply due to not having the main water supply turned on..
INSP-Sprinkler Rough-in11/1/201011/2/201011/2/2010APASS
DetailsTroy Cobbley
The underground supply piping is ok to cover.
INSP-Conference10/18/201010/18/201010/19/2010PDONE
DetailsTroy Cobbley
Bill and I went over earthquake bracing. I told him if the earthquaking did not match plans then resubmittals of the seismic calculations would be required. We also talked about possible z-purlin manufacture approval for earthquake attachment.
Issue and Print Permit  9/16/2010 DONE
Sprinkler Plan Check9/15/2010 9/15/2010 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  9/15/2010 DONE
DetailsTim Frost
Inspection Record Card- Fire9/15/2010 9/15/2010 DONE
DetailsBarbara Stitt
Permit Ready to Issue  9/15/2010 DONE
DetailsBarbara Stitt
Telephone call  9/15/2010 DONE
DetailsBarbara Stitt
Called Shaun Ramsey and told him that permit is ready & fees due on 9-15-10 @ 3:50pm
Plan assigned to (Tim)8/13/2010 9/15/2010 DONE
DetailsTim Frost
9/15/2010 11:21:29 TRF - activity updated through activity FIRA22 from case FIR10-00400.
Plan resubmittals received  9/10/2010 DONE
DetailsTisha Gallop
received three copies of application, submittal doucments and plans; taken to fire review.
Sprinkler Plan Check9/8/2010 9/8/2010 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
Telephone call  9/8/2010 DONE
left vm for shaun at ###-#### x 229 - permit denied - needs to be picked up and resubmitted
Miscellaneous action  9/8/2010 DONE
Emailed review to contractor
Plan resubmittals received  8/31/2010 DONE
received 3 sets of plans and applications sent to Tim Frost
Case Summary  8/19/2010 DONE
Miscellaneous action  8/19/2010 DONE
picked up denied plans
Sprinkler Plan Check8/17/2010 8/17/2010 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  8/17/2010 DONE
DetailsTim Frost
Miscellaneous action  8/17/2010 DONE
Emailed review to contractor
Telephone call  8/17/2010 DONE
t/c w shaun at ###-#### - permit denied - needs to be picked up and resubmitted
Application received  8/13/2010