Permit Information
Permit NumberFIR10-00415
StatusFinaled
Name DOHERTY ELECTRIC
Site Address 950 W STATE ST
Project NameFirst Presbyterian Church TI
Customer Number 
ePlanReviewNo
Description
1-26-11 PLAN MODIFICATION (no initiating devices affected): This plan modification is to incorporate field changes and implemented redlines and review comments from previous reviews.

10-5-10:This fire alarm permit is to provide speaker strobes throughout the new tenant improvement area, a new duct detector, and relocation/re-mounting of existing pull stations to meet current ADA requirements.
Associated building permit: BLD10-00842 (FIRST PRESBYTERIAN CHURCH - LINDSAY HALL REMODEL) Fire sprinklers used for building area increase. To remodel the basement (3,528 square feet), first story (3,528 square feet), and second story (3,528 square feet) of the existing Lindsay Hall portion (East end of building) of the First Presbyterian Church. Work is to include upgrading the restrooms on all 3 stories to be accessible to the disabled, upgrading the enclosure of the East stairway to be 1-hr fire-resistance-rated, constructing interior walls, installing new folding partitions, and creating new openings in an existing masonry wall (steel headers and trimmers). Work also includes exterior windows, doors, suspended acoustical ceilings, interior finishes, and millwork. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. Lindsay Hall will be fully fire sprinklered throughout in conjunction with this permit. The fire sprinkler system of the entire First Presbyterian Church building is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  6/15/2011 DONE
Drawings taken to records for scanning.
Miscellaneous action  6/15/2011 DONE
Drawings taken to records for scanning.
INSP-Final Inspection3/22/20113/24/20113/24/2011APASS
DetailsForrest France
Corrections finished. Fire alarm passed final inspection.
INSP-Final Inspection3/15/20113/17/20113/17/2011AFAIL
DetailsForrest France
Speakers are not operational.
INSP-Final Inspection3/14/20113/15/20113/15/2011ACANC
DetailsForrest France
7:30am if possible. Nick is the contact his no. is ###-####. Phone #: ###-#### >> Inspection requested via web by Shawna Gates Inspection cancelled from web by: Shawna Gates
INSP-Final Inspection2/9/20112/14/20112/14/2011AFAIL
DetailsForrest France
C/N items include; pressure switch at the dry system must report as an alarm condition and initiate activation of the outside bell, adjust cd settings at the first floor vestibule and adjacent to the reception desk per plan, provide notification at the employee work room per plan review red line notes, mechanical room duct detector activates general alarm condition, provide a WP notification appliance at the 2nd floor shower room, replace 15cd strobe only per plan at the 2nd floor west corridor. KH monitor tested okay, remainder of fire sprinkler riser points also okayed.
INSP-Sprinkler Rough-in/Hydro2/9/20112/14/20112/9/2011ACANC
DetailsForrest France
Please schedule for 7:30am. Rafe with Protex is the contact his cell no. is ###-####. Thank you.
Phone #: ###-#### >> Inspection requested via web by Shawna Gates Inspection cancelled from web by: Shawna Gates
INSP-Final Inspection1/27/20112/1/20111/31/2011ANR
DetailsForrest France
INSP-Final Inspection1/27/20111/28/20111/27/2011ACANC
DetailsForrest France
Request for 7:30am inspection. Rafe with Protex is the contat, his cell no. is ###-####. Phone #: ###-#### >> Inspection requested via web by Shawna Gates Inspection cancelled from web by: Shawna Gates
Plan assigned to (Stephanie)1/24/2011 1/26/2011 DONE
DetailsStephanie L. Cobbley
Alarm Plan Check1/26/2011 1/26/2011 PASS
DetailsStephanie L. Cobbley
Approved with redlines and review comments.
PLANS TAKEN FRONT DESK ALARM  1/26/2011 DONE
Redlined approved plans available at front counter.
Inspection Record Card- Fire1/26/2011 1/26/2011 DONE
DetailsPatricia Smith
Telephone call  1/26/2011 DONE
t/c w mike - permit (plan mod) ready and fees given
Permit Ready to Issue  1/26/2011 DONE
Details
CHANGE STATUS TO (ISS)  1/26/2011 DONE
DetailsBarbara Stitt
(F) Reprint permit  1/26/2011 DONE
DetailsBarbara Stitt
Plan resubmittals received  1/24/2011  
INSP-Alarm Testing11/15/201011/15/201011/16/2010PPART
DetailsForrest France
Notification testing at the basement level previously completed- ref. building permit activity notes.
Meeting  10/12/2010 DONE
Tom Gainor and I met with the fire alarm contractor, electrical contractor, general contractor, architect, and the building representative to set off the existing fire alarm system. The intent was to determine if the existing horns would inhibit the intelligibility of the speakers within the Lindsay Hall area of work. It was determined that the devices with horns on the 'border' of the scope of work would need to be replaced with either strobe only devices (in areas already containing speakers), or combination speaker/strobes (in areas not already equipped with speakers). It was also stated that if, during the inspection, the inspector determines other devices need to be replaced due to intelligibility issues within the scope of work, then it would need to be done prior to signing off the permit. I let the contractors know that the changes could all be implemented in the field, and then upon completion of the installation, they would need to submit all the changes in a plan modification prior to calling for a final inspection.
Miscellaneous action  10/12/2010 DONE
During a site visit of the scope of work, it was noted that several of the existing areas had intelligibility problems due to a combination of horn/strobes and speaker/strobes being installed in the same spaces. It was also noted that some of the existing combination horn/strobe devices had the 'horn' portion of the device disconnected. Tom Gainor and I informed the contractors that the areas did not meet the code the system was installed under, and that they may be required to correct those spaces. We also notified the contractors that code does not allow disconnecting a portion of the device due to the product listing and problems with having a 'presumed' device that is not fully operational. I told the contractors that as long as the existing devices did not disrupt the intelligibility or operation of the devices within the scope of work of the Lindsay Hall permit, then it would not prevent the permit from being signed off. The issue of the problems with the existing notification has been handed off to the fire department for further review.
Issue and Print Permit  10/7/2010 DONE
Inspection Record Card- Fire10/6/2010 10/6/2010 DONE
DetailsPatricia Smith
Telephone call  10/6/2010 DONE
t/c w mike at ###-#### - permit ready and fees given
Permit Ready to Issue  10/6/2010 DONE
Details
Telephone call  10/5/2010 DONE
Rob Ahten called to let me know he'd like me to approved the submittals and understands that a plan modification will be required (subject to additional review fees). He also requested a meeting with Scott A. and I, along with the general contractor and architect to address the existing horn/strobe vs. speaker/strobe issue. I let him know that I would get with Scott regarding his schedule and email and/or call him back.
Miscellaneous action  10/5/2010 DONE
Sent Rob Ahten an email stating that PDS Fire Alarm Plan review and Boise City Fire Dept. want to schedule a time to go to the site to set off the fire alarm system and walk through the building to determine intelligibility and/or any problems with intelligibility. Although the main focus will be on Lindsay Hall, we will need access to the entire building (all rooms and areas). I asked him to please choose either this Friday (October 8th) or Tuesday, Thursday, or Friday of next week (October 12th, 14th, or 15th). Early morning is preferred if possible. I let him know that the meeting he requested can be done at this time as well. I also reitterated as a side note that the fire alarm plans will be approved with notes/comments, and with the understanding that a plan modification will be required to be submitted and approved prior to calling for a final inspection. I stated additional review fees will apply.
Alarm Plan Check10/5/2010 10/5/2010 PASS
DetailsStephanie L. Cobbley
see review comments and redlines. A plan modification will be required prior to calling for a final inspection
PLANS TAKEN FRONT DESK ALARM  10/5/2010 DONE
Approved redlined plans available at front counter
Plan assigned to (Stephanie)8/23/2010 10/5/2010 DONE
DetailsStephanie L. Cobbley
Telephone call  10/4/2010 DONE
Spoke with Mike Bayse regarding discrepencies in the plans. I let him know there were several items from the first review that were not addressed in the resubmittal. I told him I could go ahead and approve them with the understanding that a plan modification (with additional review fees) would need to be submitted and approved prior to final inspection; or, I could reject these and they could resubmit, thereby only paying one review fee. Mike requested that I approve the drawings with the understanding a plan modification will be submitted and approved prior to calling for a final inspection (additional review fees will apply)
Telephone call  10/4/2010 DONE
Recieved a phone call (after the phone call was made to Mike Bayse) from Rob Ahten asking me to please wait to approve or reject the plans until tomorrow.
Plan resubmittals received  9/30/2010  
DetailsStephanie L. Cobbley
rec'd 2 sets
1st review completed  8/31/2010 DONE
Alarm Plan Check8/31/2010 8/31/2010 FAIL
DetailsStephanie L. Cobbley
Plans denied. See redlines and review comments.
Telephone call  8/31/2010 DONE
Spoke to architect and fire alarm contractor regarding the changes that need to be made and let them know a resubmittal is required.
Miscellaneous action  8/31/2010 DONE
Faxed review comments of the denied plans to the applicant
Miscellaneous action  8/31/2010 DONE
placed denied plans and comments at the front counter for customer pick-up.
Application received  8/23/2010