Miscellaneous action | | | 6/15/2011 | | DONE |
|
|
|
Drawings taken to records for scanning.
|
INSP-Final Inspection | 3/3/2011 | 3/3/2011 | 3/3/2011 | P | PASS |
Forrest France
|
|
|
Scope of permit work passed functional testing at three ADA unit restrooms. Plan resubmital verified, permit finaled.
|
CHANGE STATUS TO (ISS) | | | 3/3/2011 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 3/3/2011 | | DONE |
Barbara Stitt
|
|
|
|
Alarm Plan Check | 3/2/2011 | | 3/2/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Plan modification approved
|
PLANS TAKEN FRONT DESK ALARM | | | 3/2/2011 | | DONE |
|
|
|
Approved plan modification documents available at front counter
|
Permit Ready to Issue | | | 3/2/2011 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 3/2/2011 | | 3/2/2011 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 3/2/2011 | | DONE |
Barbara Stitt
|
|
|
Left message for Robert King that permit is ready & fees due on 3-2-11 @ 4:10pm///BAS
|
Plan assigned to (Stephanie) | 2/24/2011 | | 3/2/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Plan resubmittals received | | | 2/24/2011 | | |
Barbara Stitt
|
|
|
|
FIR-Aging Inspection | 2/15/2011 | 2/15/2011 | 2/15/2011 | | FAIL |
Forrest France
|
|
|
Ref. correction notice items.
|
INSP-Final Inspection | 12/13/2010 | 12/13/2010 | 12/13/2010 | P | FAIL |
Troy Cobbley
|
|
|
The NAC circuit did not report a trouble to the FACP. The FACP did not report a trouble to the monitoring station and did not activate a trouble signal at the remote annunciator. This is a requirement of NFPA 72 4.4.7.1. The sprinkler tamper switches reported a toruble signal at the remote annunciator and at the monitoring station. The lenses of the new strobes are not mounted between 80" and 96". Also as-builts are needed which show all of the existing a/v's remaining on the existing panel and only the three new a/v's being added to the new NAC panel. Revised EOL voltage drop calculations are needed and battery calculations are needed. There was no actual testing of devices.
|
INSP-Final Inspection | 12/6/2010 | 12/7/2010 | 12/8/2010 | P | NH |
Forrest France
|
|
|
|
Issue and Print Permit | | | 10/13/2010 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Stephanie) | 8/30/2010 | | 10/8/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Miscellaneous action | | | 10/8/2010 | | DONE |
|
|
|
Quick permit changed to regular permit due to extent of work being done.
|
Alarm Plan Check | 10/8/2010 | | 10/8/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved with comments
|
PLANS TAKEN FRONT DESK ALARM | | | 10/8/2010 | | DONE |
|
|
|
Approved plans available at front counter
|
Inspection Record Card- Fire | 10/8/2010 | | 10/8/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 10/8/2010 | | DONE |
|
|
|
t/c w shelly at ###-####- permit ready and fees given
|
Permit Ready to Issue | | | 10/8/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/4/2010 | | |
Barbara Stitt
|
|
|
|
1st review completed | | | 9/2/2010 | | DONE |
|
|
|
|
Alarm Plan Check | 9/2/2010 | | 9/2/2010 | | FAIL |
Stephanie L. Cobbley
|
|
|
Quick permit denied. Plans do not meet code requirements for hotel rooms w/ADA requirements.
|
Telephone call | | | 9/2/2010 | | DONE |
|
|
|
Spoke with Robert to let him know why the plans were being denied.
|
Miscellaneous action | | | 9/2/2010 | | DONE |
|
|
|
Faxed Robert with Taylor Brothers the first sheet of his submitted application with comments explaining some of why the plans were being denied.
|
Application received | | | 8/30/2010 | | |
|
|
|
|