Miscellaneous action | | | 6/8/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 1/20/2011 | 1/20/2011 | 1/20/2011 | A | PASS |
Forrest France
|
|
|
Correction items verified for completion. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 1/18/2011 | 1/19/2011 | 1/19/2011 | A | CANC |
Forrest France
|
|
|
I''m coming from Kuna please give me atleast a 30 minute heads up. Thx, Clarence Phone #: ###-#### >> Inspection requested via web by Clarence McLain Inspection cancelled from web by: John Venche
|
INSP-Sprinkler Rough-in/Hydro | 1/13/2011 | 1/14/2011 | 1/14/2011 | A | PART |
Troy Cobbley
|
|
|
Overhead hydrostatic test completed satisfactory per inspector 410.
|
INSP-Sprinkler Rough-in/Hydro | 1/12/2011 | 1/13/2011 | 1/13/2011 | P | PART |
Forrest France
|
|
|
Underground fire supply line hydrostatic test completed acceptable.
|
INSP-Final Inspection | 1/12/2011 | 1/13/2011 | 1/13/2011 | P | NR |
Forrest France
|
|
|
Missing field ceiling tile, escutcheons, DCVA certification, forward flow, etc.
|
INSP-Sprinkler Rough-in | 12/27/2010 | 12/28/2010 | 12/28/2010 | A | PART |
Forrest France
|
|
|
Overhead rough-in approved for cover at the office area grid ceilings. Need to provide coverage below the 6'x6' hood at the shop bay, include seismic clearance at main penetrations through non-frangible wall construction, install correct temp. rated heads within the zone of influence at unit heaters in the shop areas (SW and uprights).
|
INSP-Sprinkler Rough-in | 12/16/2010 | 12/17/2010 | 12/17/2010 | A | DEFR |
Forrest France
|
|
|
Inspection postponed due to jobsite condtions and access to city approved plan set on site.
|
Plan assigned to (Tim) | 12/9/2010 | | 12/13/2010 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/13/2010 | | 12/13/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 12/13/2010 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/13/2010 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 12/13/2010 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/13/2010 | | 12/13/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 12/13/2010 | | DONE |
|
|
|
t/c w clarence at ###-#### - permit (plan mod) ready and fees given
|
(F) Reprint permit | | | 12/13/2010 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/13/2010 | | |
|
|
|
|
Plan resubmittals received | | | 12/9/2010 | | DONE |
Tisha Gallop
|
|
|
Plan Modifcation: received three copies of application, submittal documents and plans; routed to Fire Review.
|
INSP-Supply line flush | 12/1/2010 | 12/2/2010 | 12/6/2010 | P | PART |
Forrest France
|
|
|
Underground fire supply line flush completed acceptable.
|
INSP-Supply line flush | 11/30/2010 | 12/1/2010 | 12/1/2010 | P | CANC |
Forrest France
|
|
|
Phone #: ###-#### >> Inspection requested via web by John Venche Inspection cancelled from web by: John Venche
|
INSP-Sprinkler Rough-in/Hydro | 10/12/2010 | 10/13/2010 | 10/13/2010 | P | FAIL |
Forrest France
|
|
|
UG fire supply line hydrostatic test failed due to pressure loss below 200 psi at the guage.
|
INSP-Sprinkler Rough-in/Hydro | 10/13/2010 | 10/13/2010 | 10/13/2010 | A | PART |
Forrest France
|
|
|
Underground fire supply line is approved for bury. Need to provide method for seismic clearance at the floor slab. Discussed fire code review notes regarding PI valves and riser room ratings.
|
Issue and Print Permit | | | 9/14/2010 | | |
|
|
|
|
Sprinkler Plan Check | 9/13/2010 | | 9/13/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/13/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 9/13/2010 | | 9/13/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 9/13/2010 | | DONE |
|
|
|
t/c w clarence at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 9/13/2010 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 8/31/2010 | | 9/13/2010 | | DONE |
Tim Frost
|
|
|
9/13/2010 14:11:21 TRF - activity updated through activity FIRA22 from case FIR10-00425.
|
Miscellaneous action | | | 9/10/2010 | | DONE |
|
|
|
denied plans picked up by contractor
|
Plan resubmittals received | | | 9/10/2010 | | DONE |
Tisha Gallop
|
|
|
received three copies of application, submittal documents and plans; taken to fire review.
|
Sprinkler Plan Check | 9/7/2010 | | 9/7/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 9/7/2010 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 9/7/2010 | | DONE |
|
|
|
t/c w clarence at ###-#### - permit denied - needs to be picked up and resubmitted
|
Application received | | | 8/31/2010 | | |
|
|
|
|
Pending Assignment by SAM | 8/31/2010 | | 8/31/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
8/31/2010 11:37:29 ALR - activity updated through activity FIRA158 from case FIR10-00425.
|