Miscellaneous action | | | 1/14/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 12/15/2010 | 12/16/2010 | 12/16/2010 | A | PASS |
Forrest France
|
|
|
Final inspection passed, permit finaled.
|
INSP-Sprinkler Rough-in | 12/14/2010 | 12/14/2010 | 12/14/2010 | P | PART |
Forrest France
|
|
|
Adjustments underway.
|
INSP-Final Inspection | 12/14/2010 | 12/14/2010 | 12/14/2010 | P | NR |
Forrest France
|
|
|
|
INSP-Final Inspection | 12/7/2010 | 12/9/2010 | 12/9/2010 | A | FAIL |
Troy Cobbley
|
|
|
A soffit has been installed against the south wall which is causing an obstruction. The pendant heads will not provide coverage beneath it. This obstruction was not shown on the approved sprinkler plans. Also the flow switch needs to be tested through an approved orfice. The approved plans show a bell on the new office but one has not been installed. Per Tim Frost this new flow switch can be wired into the existing bell on the existing house.
|
FIR-Aging Inspection | 12/2/2010 | 12/2/2010 | 12/2/2010 | | DONE |
Forrest France
|
|
|
Site work in progress
|
INSP-Sprinkler Rough-in | 9/28/2010 | 9/29/2010 | 9/30/2010 | P | PART |
Forrest France
|
|
|
Overhead rough-in completed acceptable. Installation okayed for cover.
|
Issue and Print Permit | | | 9/16/2010 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 9/8/2010 | | 9/15/2010 | | DONE |
Tim Frost
|
|
|
9/15/2010 13:33:12 TRF - activity updated through activity FIRA22 from case FIR10-00447.
|
Plan resubmittals received | | | 9/15/2010 | | |
Tim Frost
|
|
|
rec'd 3 sets
|
Sprinkler Plan Check | 9/15/2010 | | 9/15/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/15/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 9/15/2010 | | 9/15/2010 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 9/15/2010 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 9/15/2010 | | DONE |
Barbara Stitt
|
|
|
Left voice message for Keith Dilworth that permit is ready & fees due on 9-15-10 @ 3:35pm
|
Sprinkler Plan Check | 9/13/2010 | | 9/13/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are annotations on the plans.
|
1st review completed | | | 9/13/2010 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 9/13/2010 | | DONE |
|
|
|
Emailed review to contractor.
|
Telephone call | | | 9/13/2010 | | DONE |
|
|
|
left vm for shaun at ###-#### - permit denied - needs to be picked up and resubmitted
|
Application received | | | 9/8/2010 | | |
|
|
|
|
Pending Assignment by SAM | 9/8/2010 | | 9/8/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
9/8/2010 09:26:32 ALR - activity updated through activity FIRA158 from case FIR10-00447.
|