INSP-Final Inspection | 12/28/2010 | 12/30/2010 | 12/30/2010 | A | PASS |
Forrest France
|
|
|
Fire sprinkler work passed inspection.
|
Sprinkler Plan Check | 12/9/2010 | | 12/9/2010 | | PASS |
Troy Cobbley
|
|
|
Approved on Site
|
1st review completed | | | 12/9/2010 | | DONE |
Troy Cobbley
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/9/2010 | | DONE |
Troy Cobbley
|
|
|
|
Issue and Print Permit | | | 12/9/2010 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/2/2010 | | 12/2/2010 | | FAIL |
Troy Cobbley
|
|
|
Provide revised scope of work. Provide updated plan with fire extinguisher symbol and shaded wall removed.
|
Sprinkler Plan Check | 9/13/2010 | | 9/13/2010 | | DONE |
Troy Cobbley
|
|
|
Approved on site
|
Issue and Print Permit | | | 9/13/2010 | | DONE |
|
|
|
per trf
|
Plan assigned to (Scott) | | | 9/8/2010 | | DONE |
Bill Alexander
|
|
|
This permit was created on the web by Paul Marcolina
|
Application received | | | 9/8/2010 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|