INSP-Final Inspection | 12/9/2010 | 12/9/2010 | 12/9/2010 | P | PASS |
Forrest France
|
|
|
Noted correction item verified for completion, fire sprinkler permit finaled.
|
INSP-Final Inspection | 11/22/2010 | 11/23/2010 | 11/23/2010 | A | PART |
Forrest France
|
|
|
Scope of overhead modifications approved for ceiling cover. Final pending coverage adjustment at one area adjacent to the SW exit of the remodel.
|
INSP-Sprinkler Rough-in/Hydro | 11/8/2010 | 11/9/2010 | 11/9/2010 | P | NR |
Forrest France
|
|
|
Project not in condition for a rough-in inspection at this time. Ceiling grid and new pendent heads are not yet installed at several areas.
|
Sprinkler Plan Check | 9/13/2010 | | 9/13/2010 | | DONE |
Troy Cobbley
|
|
|
Approved on site
|
Issue and Print Permit | | | 9/13/2010 | | DONE |
|
|
|
per trf
|
Plan assigned to (Scott) | | | 9/8/2010 | | DONE |
Bill Alexander
|
|
|
This permit was created on the web by Paul Marcolina
|
Application received | | | 9/8/2010 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|