CHANGE STATUS TO (COL) | | | 6/24/2011 | | DONE |
|
|
|
|
Miscellaneous action | | | 6/8/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 4/22/2011 | 4/22/2011 | 4/22/2011 | P | PASS |
Forrest France
|
|
|
john Phone #: ###-####
|
INSP-Final Inspection | 4/20/2011 | 4/21/2011 | 4/21/2011 | A | CANC |
Troy Cobbley
|
|
|
Unable to final until the interconnections with the fire alarm panel can be tested.
|
INSP-Final Inspection | 4/15/2011 | 4/18/2011 | 4/18/2011 | A | CANC |
Troy Cobbley
|
|
|
Canceled per jeff Phone #: ###-####
|
INSP-Final Inspection | 4/14/2011 | 4/15/2011 | 4/15/2011 | A | CANC |
Troy Cobbley
|
|
|
jeff Phone #: ###-####
|
INSP-Sprinkler Rough-in | 4/6/2011 | 4/6/2011 | 4/7/2011 | P | PASS |
Troy Cobbley
|
|
|
the earthquake bracing has been corrected and the front canopy has been reduced to less than 160 cubic feet
|
INSP-Sprinkler Rough-in/Hydro | 3/30/2011 | 3/30/2011 | 3/30/2011 | P | PASS |
Troy Cobbley
|
|
|
hydro test passed except for the FDC piping which was not put under the test.
|
INSP-Sprinkler Rough-in | 3/11/2011 | 3/14/2011 | 3/16/2011 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping above the ceilings in the combustible areas is ok to cover.
|
Sprinkler Plan Check | 3/11/2011 | | 3/11/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/11/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 3/11/2011 | | 3/11/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 3/11/2011 | | DONE |
|
|
|
t/c w shaun - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 3/11/2011 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/11/2011 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 3/11/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 2/22/2011 | | 3/11/2011 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 3/9/2011 | | DONE |
Christina Prado
|
|
|
Received 3 copies of application, checklist, calcs and previously denied plans. As well as 3 copies of plans FP1 and FP3. Routed to Tim Frost for review
|
Sprinkler Plan Check | 2/23/2011 | | 2/23/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 2/23/2011 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 2/23/2011 | | DONE |
|
|
|
Emailed review comments to contractor.
|
Telephone call | | | 2/23/2011 | | DONE |
|
|
|
t/c w shawn - permit denied - needs to be picked up and resubmitted
|
Plan resubmittals received | | | 2/22/2011 | | DONE |
Tisha Gallop
|
|
|
Plan modification accepted
|
INSP-Sprinkler Rough-in | 2/2/2011 | 2/2/2011 | 2/2/2011 | P | FAIL |
Troy Cobbley
|
|
|
There were no city approved plans on site to perform an inspection. Per the sprinkler fitter the plans do not show the combustible construction or any of the upright sprinkler protection that the fitter has added. I let the fitter know that resubmittals of the plans will be required. We discussed the possible obstruction to upright sprinkler discharge and the associated "three times rule". No inspection was performed.
|
Sprinkler Plan Check | 11/16/2010 | | 11/16/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments. There are approved as noted comments in the review.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/16/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 11/16/2010 | | 11/16/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 11/16/2010 | | DONE |
|
|
|
t/c w aleshia - permit ready and fees given
|
Permit Ready to Issue | | | 11/16/2010 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/16/2010 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 11/10/2010 | | 11/16/2010 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 11/10/2010 | | |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 10/15/2010 | | 10/28/2010 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 10/27/2010 | | |
|
|
|
received 3 sets of plans / applications sent to Tim F for review
|
Sprinkler Plan Check | 10/18/2010 | | 10/18/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 10/18/2010 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 10/18/2010 | | DONE |
|
|
|
left vm for keith at ###-#### - permit denied - needs to be picked up and resubmitted
|
Case Summary | | | 10/15/2010 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | | 10/15/2010 | | |
|
|
|
|