Miscellaneous action | | | 10/13/2011 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 9/13/2011 | 9/13/2011 | 9/13/2011 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Alarm Testing | 9/12/2011 | 9/13/2011 | 9/13/2011 | A | DONE |
Troy Cobbley
|
|
|
Testing is done. Wrong inspection type called in.
|
INSP-Final Inspection | 4/14/2011 | 4/15/2011 | 4/15/2011 | P | FAIL |
Troy Cobbley
|
|
|
Provide map at the facp. All other items ok.
|
Issue and Print Permit | | | 12/8/2010 | | DONE |
Barbara Stitt
|
|
|
|
Alarm Plan Check | 11/30/2010 | | 11/30/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
approved - see review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 11/30/2010 | | DONE |
|
|
|
approved plans available at front counter
|
Inspection Record Card- Fire | 11/30/2010 | | 11/30/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 11/30/2010 | | DONE |
|
|
|
t/c w john - permit ready and fees given
|
Permit Ready to Issue | | | 11/30/2010 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 10/22/2010 | | 11/30/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Plan resubmittals received | | | 11/24/2010 | | |
Barbara Stitt
|
|
|
|
Case Summary | | | 11/24/2010 | | |
Barbara Stitt
|
|
|
|
Alarm Plan Check | 11/19/2010 | | 11/19/2010 | | FAIL |
Stephanie L. Cobbley
|
|
|
Plans denied - see review comments
|
Telephone call | | | 11/19/2010 | | DONE |
|
|
|
Spoke to John L. at FSS to let him know the plans were being denied and why. I let him know his set of plans would be at the front counter for pick-up.
|
Miscellaneous action | | | 11/19/2010 | | DONE |
|
|
|
Denied plans available at front counter
|
Telephone call | | | 11/17/2010 | | DONE |
|
|
|
Spoke with John at FSS to let him know I need a floorplan showing the actual location of the duct detector - it is not acceptable to show the device in a general area on the site plan.
|
Plan resubmittals received | | | 11/15/2010 | | DONE |
Tisha Gallop
|
|
|
received two copies of application, submittal folder and plans; taken to SLC
|
Alarm Plan Check | 11/10/2010 | | 11/10/2010 | | FAIL |
Stephanie L. Cobbley
|
|
|
No written review comments. Plans denied. Contractor is going to resubmit with a duct detector added to comply with a previous building permit requirement (BLD08-01564).
|
Miscellaneous action | | | 11/10/2010 | | DONE |
|
|
|
Denied plans available at front counter
|
1st review completed | | | 11/5/2010 | | DONE |
|
|
|
|
Telephone call | | | 11/5/2010 | | DONE |
|
|
|
Spoke to John with Fire Sentry to let him know I can not approve the fire alarm plans because there is an open building permit (BLD08-01564) that needs to be finaled first. That building permit was not finaled because under the permit a 10-ton HVAC unit was installed over the gym with a duct detector that needs to be tied in to the existing fire alarm system. A fire permit for that work has never been pulled. I explained to John that that will need to be addressed before I can pass this permit. I let him know it could be done under a separate permit, or I could fail this one and he could resubmit with the duct detector work so only one review fee would apply. I also let John know that, while it was approved under the original permit to allow the main building and portable building to have two independent fire alarm systems, it would be highly recommended to tie in the panels so that the main panel could monitor alarm, trouble, and supervisory functions of the portable's panel. I reiterated that the 'tie-in' would not be a required issue or hold up this permit due to previous agreements, but that for public safety reasons it really should be done. He stated he would let me know next week which route they'd like to take.
|
Application received | | | 10/22/2010 | | |
|
|
|
|