Miscellaneous action | | | 9/22/2011 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 8/25/2011 | 8/25/2011 | 8/25/2011 | P | PASS |
Forrest France
|
|
|
C/N items field verified for completion. Fire sprinkler permit approved for final.
|
INSP-Final Inspection | 8/18/2011 | 8/19/2011 | 8/19/2011 | A | PART |
Forrest France
|
|
|
Items which remain for final include; ceilings at the bike and storage rooms- remove travel caps and install escutcheons on sw heads, remove thermal elements at the four deluge heads on the 1st floor, missing escutcheon at the 3rd floor, noted one closet at AV 222 missing coverage.
|
INSP-Final Inspection | 8/17/2011 | 8/18/2011 | 8/18/2011 | A | PART |
Forrest France
|
|
|
|
INSP-Final Inspection | 8/4/2011 | 8/9/2011 | 8/9/2011 | A | NR |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 7/28/2011 | 7/28/2011 | 7/28/2011 | A | PART |
Forrest France
|
|
|
Hydrostatic testing finished.
|
INSP-Sprinkler Rough-in/Hydro | 7/27/2011 | 7/27/2011 | 7/27/2011 | P | PART |
Forrest France
|
|
|
OH hydrostatic testing finished for the 1st, 2nd, and 3rd floor systems including the deluge valve and standpipe.
|
INSP-Sprinkler Rough-in | 7/19/2011 | 7/20/2011 | 7/21/2011 | A | PART |
Forrest France
|
|
|
Remainder of overhead fire sprinkler work at the 3rd floor approved for cover with the exception of two pendent heads at corridor 328 obstructed by an adjacent soffit.
|
INSP-Sprinkler Rough-in/Hydro | 7/19/2011 | 7/20/2011 | 7/20/2011 | A | CANC |
Forrest France
|
|
|
bryan Phone #: ###-####
|
INSP-Sprinkler Rough-in | 7/14/2011 | 7/15/2011 | 7/15/2011 | P | PART |
Forrest France
|
|
|
Perimeter rooms at the third floor as marked on plans okayed for ceiling cover.
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2011 | 7/11/2011 | 7/11/2011 | P | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 7/1/2011 | 7/5/2011 | 7/6/2011 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the second floor areas where the sprinkler piping can be covered. Earthquaking has been fixed.
|
INSP-Sprinkler Rough-in | 6/30/2011 | 7/1/2011 | 7/1/2011 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the second floor areas that are ok to cover.
|
INSP-Sprinkler Rough-in | 6/9/2011 | 6/9/2011 | 6/9/2011 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans marked with todays date where piping is ok to cover. This included gridded areas on both sides of the south lobby.
|
INSP-Sprinkler Rough-in | 6/3/2011 | 6/3/2011 | 6/3/2011 | P | PART |
Forrest France
|
|
|
Overhead fire sprinkler work at the first floor classrooms 114 and 107 and restrooms 111 and 112 are okay to cover at the drop ceilings. See clouded areas on plan set with today's date.
|
INSP-Sprinkler Rough-in | 5/5/2011 | 5/5/2011 | 5/6/2011 | P | PART |
Forrest France
|
|
|
Preaction system piping at the second floor computer room approved for cover- see dated annotation on plans.
|
INSP-Sprinkler Rough-in/Hydro | 4/21/2011 | 4/21/2011 | 4/21/2011 | A | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 4/19/2011 | 4/20/2011 | 4/20/2011 | A | PART |
Forrest France
|
|
|
See annotations on stamped plan set for areas on the 3rd floor okayed to cover with hard lid ceilings.
|
INSP-Sprinkler Rough-in | 4/8/2011 | 4/8/2011 | 4/8/2011 | P | PART |
Forrest France
|
|
|
Overhead rough-in above hard lid ceilings as marked on plans with today's date for the first and second floors approved for cover.
|
INSP-Sprinkler Rough-in | 4/6/2011 | 4/7/2011 | 4/8/2011 | P | PART |
Forrest France
|
|
|
Upright protection verified at the first floor link above the sheetrock ceiling.
|
INSP-Sprinkler Rough-in | 3/31/2011 | 4/1/2011 | 4/1/2011 | P | PART |
Forrest France
|
|
|
See approved plan set for locations okayed for sheetrock ceiling cover at the 1st floor only- marked with today's date. Upright protection to be added at one area as marked.
|
Sprinkler Plan Check | 3/22/2011 | | 3/22/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 3/22/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/22/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 3/22/2011 | | 3/22/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 3/22/2011 | | DONE |
|
|
|
t/c w sam - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 3/22/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/22/2011 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/18/2011 | | DONE |
|
|
|
received 3 sets of resubmitted plans and applications sent to Tim Frost
|
INSP-Final Inspection | 3/9/2011 | 3/10/2011 | 3/10/2011 | A | PART |
Forrest France
|
|
|
Underground fire supply line flushing completed satisfactory.
|
INSP-Sprinkler Rough-in | 2/7/2011 | 2/8/2011 | 2/8/2011 | A | PART |
Forrest France
|
|
|
Inspection for beam clamp retainers and seismic brace attatchments at the third floor pre-fireproof coatings okayed.
|
INSP-Sprinkler Rough-in | 1/27/2011 | 1/27/2011 | 1/28/2011 | P | PART |
Tim Frost
|
|
|
Inspected the hanger attachment in the area on the second floor which will be covered with fire proofing. The attachments passed inspection.
|
INSP-Sprinkler Rough-in | 1/11/2011 | 1/11/2011 | 1/11/2011 | P | PART |
Forrest France
|
|
|
Inspection completed to verify retainer straps at beam clamps for the first floor 3" main hangers only.
|
Issue and Print Permit | | | 11/5/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (Tim) | 10/27/2010 | | 11/4/2010 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/4/2010 | | 11/4/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/4/2010 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 11/4/2010 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 11/4/2010 | | 11/4/2010 | | DONE |
Barbara Stitt
|
|
|
|
Plan resubmittals received | | | 11/2/2010 | | |
|
|
|
received 3 app/plans sent to Tim F for review
|
Sprinkler Plan Check | 11/1/2010 | | 11/1/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 11/1/2010 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 11/1/2010 | | DONE |
|
|
|
Emailed review to designer and contractor
|
Telephone call | | | 11/1/2010 | | DONE |
Barbara Stitt
|
|
|
Left a voice message for Geg Johnson that plans failed need resubmitted on 11/1/10 @ 8:25am
|
Application received | | | 10/27/2010 | | |
|
|
|
|
Pending Assignment by SAM | 10/27/2010 | | 10/27/2010 | | DONE |
Patricia Smith
|
|
|
|