Miscellaneous action | | | 2/9/2011 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 12/28/2010 | 12/29/2010 | 12/29/2010 | A | PASS |
Forrest France
|
|
|
C/N items finished, re-inspection passed. Final okay pending scanable as-built record drawings are provided including an accurate map at the panel.
|
INSP-Final Inspection | 12/27/2010 | 12/27/2010 | 12/28/2010 | P | PART |
Forrest France
|
|
|
Adjustments for final include; provide as-built drawings accurately reflecting field installation including duct detectors at RTUs 5 and 7, the deletion of one KH monitor, provide a strobe only at the wine/av room, amend visual coverage at lounge 108 due to obstruction by ceiling suspended finishes, provide a lock at the FACP circut breaker, post accurate map at the panel. Remainder of fire alarm work tested satisfactory.
|
INSP-Final Inspection | 12/8/2010 | 12/9/2010 | 12/9/2010 | A | PART |
Forrest France
|
|
|
Hood suppression and fire sprinkler riser system interconnections tested okay, offsite monitoring verified. Minor corrections and account information adjustments done while on site.
|
Issue and Print Permit | | | 12/2/2010 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Stephanie) | 11/24/2010 | | 12/1/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Telephone call | | | 12/1/2010 | | DONE |
|
|
|
Jeff with e2co returned my call and gave me the information I requested.
|
Telephone call | | | 12/1/2010 | | DONE |
|
|
|
Spoke with Ben Jackson at Peak Alarm to ask about the duct detectors. There were no data sheets provided for the duct detectors or addressable relay modules indicated for the HVAC shutdown, only monitor modules going to the duct detectors. He stated that the duct detectors are conventional devices with built in relays for HVAC shutdown, they are being provided by others with the HVAC units, and are only being monitored with the AIMs to give them addressable points.
|
1st review completed | | | 12/1/2010 | | DONE |
|
|
|
|
Alarm Plan Check | 12/1/2010 | | 12/1/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
Approved with redlines and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 12/1/2010 | | DONE |
|
|
|
Approved redlined plans available at front counter.
|
Permit Ready to Issue | | | 12/1/2010 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 12/1/2010 | | 12/1/2010 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 12/1/2010 | | DONE |
Barbara Stitt
|
|
|
Left Ben Jackson a message that permit is ready & fees due on 12-1-10 @3:15pm
|
Telephone call | | | 11/30/2010 | | DONE |
|
|
|
Left a message with Jeff S. at e2co regarding concerns I have with the ceiling plan and how it will affect the ceiling mounted horn/strobes.
|
Application received | | | 11/24/2010 | | |
|
|
|
|