INSP-Final Inspection | 8/30/2011 | 8/30/2011 | 8/31/2011 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/17/2011 | | DONE |
Troy Cobbley
|
|
|
|
Sprinkler Plan Check | 8/17/2011 | | 8/17/2011 | | PASS |
Troy Cobbley
|
|
|
|
1st review completed | | | 8/17/2011 | | DONE |
Troy Cobbley
|
|
|
|
CHANGE STATUS TO (ISS) | | | 8/17/2011 | | DONE |
|
|
|
|
INSP-Final Inspection | 8/4/2011 | 8/8/2011 | 8/8/2011 | A | PART |
Forrest France
|
|
|
Final pending revised plans for changes in head locations adjacent to room 106G.
|
Sprinkler Plan Check | 5/5/2011 | | 5/5/2011 | | PASS |
Troy Cobbley
|
|
|
|
1st review completed | | | 5/5/2011 | | DONE |
Troy Cobbley
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/5/2011 | | DONE |
Troy Cobbley
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/5/2011 | | DONE |
|
|
|
|
FIR-Aging Inspection | 3/10/2011 | 3/10/2011 | 3/10/2011 | | PEND |
Forrest France
|
|
|
Need site inspection request for permit final when complete.
|
Sprinkler Plan Check | 12/9/2010 | | 12/9/2010 | | PASS |
Troy Cobbley
|
|
|
Approved on site
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/9/2010 | | DONE |
Troy Cobbley
|
|
|
|
Issue and Print Permit | | | 12/9/2010 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/2/2010 | | 12/2/2010 | | FAIL |
Troy Cobbley
|
|
|
Resize new arm overs to match existing and show flex heads.
|
Plan assigned to (Scott) | | | 12/1/2010 | | DONE |
Bill Alexander
|
|
|
This permit was created on the web by Paul Marcolina
|
Application received | | | 12/1/2010 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|