Miscellaneous action | | | 12/16/2011 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 4/11/2011 | 4/11/2011 | 4/12/2011 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Supply line flush | 4/11/2011 | 4/11/2011 | 4/11/2011 | P | DONE |
Forrest France
|
|
|
UG supply line flush completed okay.
|
INSP-Sprinkler Rough-in | 3/7/2011 | 3/7/2011 | 3/8/2011 | P | PART |
Forrest France
|
|
|
Overhead okayed for cover per T. Frost.
|
INSP-Sprinkler Rough-in | 2/22/2011 | 2/22/2011 | 2/22/2011 | P | PASS |
Forrest France
|
|
|
Ok to cover.
don Phone #: ###-####
|
Sprinkler Plan Check | 2/16/2011 | | 2/16/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/16/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 2/16/2011 | | 2/16/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 2/16/2011 | | DONE |
|
|
|
t/c w don - permit ready and fees given
|
Permit Ready to Issue | | | 2/16/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/16/2011 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 12/15/2010 | | 2/16/2011 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 2/15/2011 | | DONE |
|
|
|
The contractor apparently sent in the wrong drawings. They were the same as the last submittal. They are going to print the correct drawings and bring to me.
|
Plan resubmittals received | | | 2/15/2011 | | DONE |
Christina Prado
|
|
|
Received new drawing requested. Three sets of FP-1. Routed to Tim for reveiw
|
Plan resubmittals received | | | 2/14/2011 | | DONE |
Tisha Gallop
|
|
|
received three copies of plans; taken to Tim Frost.
|
Miscellaneous action | | | 2/14/2011 | | DONE |
|
|
|
Received a revised drawings.
|
Miscellaneous action | | | 1/26/2011 | | PEND |
|
|
|
The project is hold pending new hydraulic calculations from Curtis.
|
Plan resubmittals received | | | 1/25/2011 | | DONE |
Tim Frost
|
|
|
Received 3 copies of application, checklist and review packet. Also received 3 copies of plans FP-1. Routed back to Tim Frost for review.
|
Sprinkler Plan Check | 12/17/2010 | | 12/17/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 12/17/2010 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 12/17/2010 | | DONE |
|
|
|
t/c w don - permit was denied - needs to be picked up and resubmitted
|
Application received | | | 12/15/2010 | | |
|
|
|
|