Miscellaneous action | | | 2/9/2011 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 1/20/2011 | 1/21/2011 | 1/21/2011 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 1/11/2011 | 1/13/2011 | 1/13/2011 | A | FAIL |
Troy Cobbley
|
|
|
Provide building map as per note 19, provide knox box per note 20, adjust the backflow tamper switch and retest, provide the correct orfice in the inspectors test and test flow switch.
|
INSP-Conference | 1/11/2011 | 1/11/2011 | 1/12/2011 | P | DONE |
Troy Cobbley
|
|
|
I spoke to the on site electrical contractor, since the general contractor was not there, about the urgency of getting permanant power to the fire alarm panel that is being replaced. The electrical contractor stated that the work would be complete within 30 minutes. A final inspection of the project related fire alarm permit has been scheduled for thursday.
|
Plan assigned to (Stephanie) | 12/30/2010 | | 1/5/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
1st review completed | | | 1/5/2011 | | DONE |
|
|
|
|
Alarm Plan Check | 1/5/2011 | | 1/5/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
plans approved with redlines and review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 1/5/2011 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Inspection Record Card- Fire | 1/5/2011 | | 1/5/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 1/5/2011 | | DONE |
|
|
|
t/c w bryan - permit ready and fees given
|
Permit Ready to Issue | | | 1/5/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/5/2011 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/5/2011 | | DONE |
|
|
|
|
Application received | | | 12/30/2010 | | |
|
|
|
|