Miscellaneous action | | | 6/15/2011 | | DONE |
|
|
|
Drawings taken to records for scanning.
|
INSP-Final Inspection | 4/19/2011 | 4/19/2011 | 4/19/2011 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
INSP-Final Inspection | 4/15/2011 | 4/18/2011 | 4/18/2011 | A | FAIL |
Troy Cobbley
|
|
|
The elevator service personell did not show up and we were unable to put the system in test. No testing was performed.
|
INSP-Final Inspection | 4/14/2011 | 4/15/2011 | 4/15/2011 | A | FAIL |
Troy Cobbley
|
|
|
Items tested today include the fire sprinkler interconnections, sync of a/v's, connection to the AES panel. Still need to do the elevator, duct detectors and end of line voltage verification, and map at the facp.
|
Issue and Print Permit | | | 1/24/2011 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Stephanie) | 1/6/2011 | | 1/21/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
1st review completed | | | 1/21/2011 | | DONE |
|
|
|
|
Alarm Plan Check | 1/21/2011 | | 1/21/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved with redlines and review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 1/21/2011 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Inspection Record Card- Fire | 1/21/2011 | | 1/21/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 1/21/2011 | | DONE |
|
|
|
t/c w doug - permit ready and fees given
|
Permit Ready to Issue | | | 1/21/2011 | | DONE |
|
|
|
|
Application received | | | 1/6/2011 | | |
|
|
|
|