Miscellaneous action | | | 6/8/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 2/18/2011 | 2/22/2011 | 2/23/2011 | A | PASS |
Forrest France
|
|
|
Final inspection passed, fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in | 2/11/2011 | 2/11/2011 | 2/11/2011 | P | PASS |
Forrest France
|
|
|
Overhead fire sprinkler system modifications per the scope of work are approved for cover at the drop ceilings.
|
Miscellaneous action | | | 2/9/2011 | | DONE |
|
|
|
The contractor verified the reference drawings to actual field conditions. The remaining area in the bldg permit scope that was not shown in the fire sprinkler scope seems to have adequate fire protecton.
|
Plan assigned to (Tim) | 1/31/2011 | | 2/8/2011 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/8/2011 | | 2/8/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 2/8/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/8/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 2/8/2011 | | 2/8/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 2/8/2011 | | DONE |
|
|
|
t/c w jim - permit ready and fees given
|
Permit Ready to Issue | | | 2/8/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/8/2011 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | | 1/31/2011 | | |
|
|
|
|