Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR11-00073
StatusFinaled
Name CURTIS FIRE SPRINKLER SERVICE INC
Site Address 9309 W FAIRVIEW AVE
Project NameMaco Spray Booth
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of adding fire sprinklers to a new spray paint booth. The fire protection system will be supplied from the existing dry system. A new supervised control valve with drain will be added near the booth, Sprinklers shall be standard response. The existing has 6” underground, 4” check valve, 4 butterfly valve and 4” dry pipe valve.

Plan Mod 1
Changed piping layout due to field conditions.


Building Department Scope:

There is no BLD associated for this project.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  6/8/2011 DONE
Sent to records for scanning.
INSP-Final Inspection3/29/20113/29/20113/29/2011PPASS
DetailsTroy Cobbley
permit finaled
Plan assigned to (Tim)3/22/2011 3/23/2011 DONE
DetailsTim Frost
Sprinkler Plan Check3/23/2011 3/23/2011 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  3/23/2011 DONE
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  3/23/2011 DONE
DetailsTim Frost
Inspection Record Card- Fire3/23/2011 3/23/2011 DONE
DetailsPatricia Smith
Telephone call  3/23/2011 DONE
t/c w don - permit (plan mod) ready and fees given
Permit Ready to Issue  3/23/2011 DONE
Details
CHANGE STATUS TO (ISS)  3/23/2011 DONE
INSP-Sprinkler Rough-in3/22/20113/22/20113/22/2011PPASS
DetailsTroy Cobbley
The overhead hydro test for the spray booth piping passed. The return bends have been installed. Awaiting the resubmittals.
INSP-Sprinkler Rough-in/Hydro3/21/20113/22/20113/22/2011AFAIL
DetailsTroy Cobbley
Plans do not match installation. Addtional heads have been added to the new piping and the sprinkler system layout does not match the city approved plans. Plans and calculations will need to be resubmitted for review. The two north most pendant heads need to be installed on return bends per NFPA 13 7.2.2 (3). No hydro test was performed due to piping modifications being required.
Plan resubmittals received  3/22/2011 DONE
DetailsChristina Prado
Received three copies of application; checklist; resubmittal letter; united water letter; #603 Hydralic Calcs; and plans FP-1. Routed to Tim Frost for review
Issue and Print Permit  2/24/2011 DONE
Plan assigned to (Tim)2/16/2011 2/17/2011 DONE
DetailsTim Frost
Sprinkler Plan Check2/17/2011 2/17/2011 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  2/17/2011 DONE
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  2/17/2011 DONE
DetailsTim Frost
Inspection Record Card- Fire2/17/2011 2/17/2011 DONE
DetailsPatricia Smith
Telephone call  2/17/2011 DONE
t/c w don - permit ready and fees given
Permit Ready to Issue  2/17/2011 DONE
Details
Application received  2/16/2011