Miscellaneous action | | | 9/2/2011 | | DONE |
|
|
|
As-built drawings received
|
Miscellaneous action | | | 9/2/2011 | | DONE |
|
|
|
Taken to records for scanning.
|
INSP-Final Inspection | 8/26/2011 | 8/29/2011 | 8/29/2011 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Override - Parcel Holds | 8/26/2011 | 1/1/1900 | 8/26/2011 | | |
|
|
|
final fire
|
INSP-Final Inspection | 8/24/2011 | 8/24/2011 | 8/24/2011 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for the the manual pull stations,elevator recall and retesting the wet sprinkler system tamper switches. A manual pull station is required at the lower level east exit doors. The tamper switches did not report to the monitoring station. The outside alarm bell now functions.
|
INSP-Final Inspection | 8/18/2011 | 8/22/2011 | 8/22/2011 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection included the fire sprinkler interconnections. The tamper switches on the wet/dry risers and low air on the dry riser passed. The wet system flow switch and the dry system pressure switch did not ring the outside alarm bell. Also a walk through on all of the notification devices was performed. See the city approved plans for items needing corrected including the need for additional strobes.
|
INSP-Final Inspection | 8/17/2011 | 8/19/2011 | 8/19/2011 | A | CANC |
Forrest France
|
|
|
Overbooked
|
INSP-Final Inspection | 8/17/2011 | 8/18/2011 | 8/18/2011 | A | CANC |
Forrest France
|
|
|
Overbooked
|
INSP-Final Inspection | 8/16/2011 | 8/17/2011 | 8/17/2011 | P | FAIL |
Troy Cobbley
|
|
|
Due to inspection load and time constraints the only items tested today were the facp and the three NAC panels. Interconnetion/supervision of these panels and phone line troubles were verified as well as the account address. Wire guage from the NAC panels was verified as well. I noted the smoke detector in the facp room is located too close to a air register.
|
Alarm Plan Check | 7/11/2011 | | 7/11/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved with redlines and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 7/11/2011 | | DONE |
|
|
|
Approved redlined plans available at front counter.
|
Inspection Record Card- Fire | 7/11/2011 | | 7/11/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 7/11/2011 | | DONE |
|
|
|
t/c w ken - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 7/11/2011 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/11/2011 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 7/11/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Stephanie) | 6/22/2011 | | 7/11/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Plan resubmittals received | | | 7/8/2011 | | DONE |
Tisha Gallop
|
|
|
received application, submittal small docs and plans; routed to Fire Review.
|
Meeting | | | 7/1/2011 | | DONE |
|
|
|
Inspector Troy Cobbley found fire alarm back boxes, wiring, and devices installed prior to having approved plans. An early start agreement is in place, however that scope of work was for fire alarm panel replacement only. A stop work order was given to general contractor superintendant with ESI. It was verbally explained to head electrical superintendant and explained to David with Allied General per a phone conversation. Double fees will apply. Per Allied General, installed devices will be removed this morning.
|
Miscellaneous action | | | 6/27/2011 | | DONE |
Tisha Gallop
|
|
|
picked up denied plans
|
Alarm Plan Check | 6/23/2011 | | 6/23/2011 | | FAIL |
Stephanie L. Cobbley
|
|
|
Plans denied - see review comments and redlines
|
Telephone call | | | 6/23/2011 | | DONE |
|
|
|
Left a message for Joe at Allied General to call regarding the plans.
|
Miscellaneous action | | | 6/23/2011 | | DONE |
|
|
|
Faxed review comments to contractor.
|
Miscellaneous action | | | 6/23/2011 | | DONE |
|
|
|
Denied plans taken to front counter for contractor to pick up.
|
Plan resubmittals received | | | 6/22/2011 | | DONE |
|
|
|
received plan modification on June 9th 2011 ///dld
|
Issue and Print Permit | | | 4/8/2011 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 3/23/2011 | | 4/1/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
1st review completed | | | 4/1/2011 | | DONE |
|
|
|
|
Alarm Plan Check | 4/1/2011 | | 4/1/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Approved with comments and redlines
|
PLANS TAKEN FRONT DESK ALARM | | | 4/1/2011 | | DONE |
|
|
|
Approved redlined plans available at front counter.
|
Inspection Record Card- Fire | 4/1/2011 | | 4/1/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 4/1/2011 | | DONE |
|
|
|
t/c w ken - permit ready and fees given
|
Permit Ready to Issue | | | 4/1/2011 | | DONE |
|
|
|
|
Early Start | | | 3/23/2011 | | DONE |
|
|
|
An early start request has been approved. See attached document.
|
Application received | | | 3/23/2011 | | |
|
|
|
|