Miscellaneous action | | | 7/8/2011 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 5/19/2011 | 5/19/2011 | 5/19/2011 | P | PASS |
Forrest France
|
|
|
Fire alarm testing completed satisfactory. Descriptor switch between the main entry and mechanical room pull station points corrected while on site. Fire alarm permit finaled.
|
CHANGE STATUS TO (ISS) | | | 5/4/2011 | | |
|
|
|
|
(F) Reprint permit | | | 5/4/2011 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 4/29/2011 | | 5/3/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | 5/3/2011 | | 5/3/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Plan modification approved with redlines and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 5/3/2011 | | DONE |
|
|
|
Approved plan modification documents available at front counter.
|
Permit Ready to Issue | | | 5/3/2011 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 5/3/2011 | | 5/3/2011 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 5/3/2011 | | DONE |
Barbara Stitt
|
|
|
Called and left a message for Brian that permit is ready & fees due on 5-3-11 @ 12:40pm
|
Plan resubmittals received | | | 4/29/2011 | | |
Barbara Stitt
|
|
|
|
INSP-Conference | 4/26/2011 | 4/26/2011 | 4/27/2011 | P | DONE |
Troy Cobbley
|
|
|
Bryan and I went over device placement changes. He wants to change device locations to ease the installation. With the location changes candella's will be effected which will effect power draw and end of line voltage. Also the pantry and the restroom located near the kitchen will require notification. Resubmittals are required to show these changes prior to inspection.
|
Inspection Record Card- Fire | 4/22/2011 | | 4/22/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 4/22/2011 | | DONE |
|
|
|
t/c w brian - permit ready and fees given
|
Permit Ready to Issue | | | 4/22/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/22/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Stephanie) | 4/6/2011 | | 4/21/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | 4/21/2011 | | 4/21/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved with redlines and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 4/21/2011 | | DONE |
|
|
|
Approved redlined plans available at front counter.
|
Miscellaneous action | | | 4/21/2011 | | DONE |
|
|
|
Recieved an email from Pastor Larry Roberts stating that there are metal lockers in place and that no personal effects would be stored in the corridors or lobbies.
|
1st review completed | | | 4/20/2011 | | DONE |
|
|
|
|
Miscellaneous action | | | 4/20/2011 | | DONE |
|
|
|
Emailed Mary Froemke (ECI) regarding protection in the corridors and requested her to let me know the direction the tenant wants to take (i.e. provide a letter from the tenant stating there would be no personal effects stored in the corridors or lobbies, provide a letter from the tenant stating personal effects would be stored in metal lockers, provide smoke detection in the corridors and areas open to the corridors, or provide a full automatic sprinkler system in the building. The review is on hold until the desired approach is communicated to me.
|
Alarm Plan Check | 4/20/2011 | | 4/20/2011 | | DEFR |
Stephanie L. Cobbley
|
|
|
on hold until further information is obtained (see comments under Misc. action)
|
Plan resubmittals received | | | 4/13/2011 | | DONE |
Tisha Gallop
|
|
|
Replacement plans received; taken to SLC.
|
Application received | | | 4/6/2011 | | |
|
|
|
|