Miscellaneous action | | | 9/22/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 8/15/2011 | 8/16/2011 | 8/16/2011 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. The forward flush passed.
|
INSP-Final Inspection | 8/12/2011 | 8/15/2011 | 8/15/2011 | P | FAIL |
Troy Cobbley
|
|
|
Need the backflow certified and forward flow tested. Also the two upright heads in the riser room are too far below the ceiling.
|
INSP-Sprinkler Rough-in/Hydro | 7/15/2011 | 7/18/2011 | 7/18/2011 | A | PASS |
Troy Cobbley
|
|
|
The above ground hydro test passed and the corrections have been made to the above ground piping. Piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 7/13/2011 | 7/14/2011 | 7/14/2011 | A | FAIL |
Troy Cobbley
|
|
|
The hydro test could not be performed due to additional upright heads required around the x-ray room and on the back side of the roof access door. Also the most current set of plans was not on site.
|
Issue and Print Permit | | | 7/12/2011 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 6/28/2011 | | 6/28/2011 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 6/28/2011 | | |
|
|
|
|
Sprinkler Plan Check | 6/28/2011 | | 6/28/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 6/28/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/28/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 6/28/2011 | | 6/28/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 6/28/2011 | | DONE |
|
|
|
t/c w cameron - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 6/28/2011 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 6/8/2011 | 6/8/2011 | 6/8/2011 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed and piping can be covered in the Entry area.
|
INSP-Sprinkler Rough-in | 6/6/2011 | 6/7/2011 | 6/7/2011 | P | PASS |
Troy Cobbley
|
|
|
Hard lid ceiling areas are ok for cover.
|
Plan assigned to (Tim) | 4/8/2011 | | 5/5/2011 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/5/2011 | | 5/5/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/5/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 5/5/2011 | | 5/5/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 5/5/2011 | | DONE |
|
|
|
t/c w cameron - permit ready and fees given
|
Permit Ready to Issue | | | 5/5/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/5/2011 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/3/2011 | | DONE |
Tisha Gallop
|
|
|
received three copies of application, submittal documents and plans; taken to fire review.
|
Sprinkler Plan Check | 4/13/2011 | | 4/13/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 4/13/2011 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 4/13/2011 | | DONE |
|
|
|
Emailed review to contractor.
|
Telephone call | | | 4/13/2011 | | DONE |
|
|
|
t/c w cameron - permit denied - needs to be picked up and resubmitted
|
Application received | | | 4/8/2011 | | |
|
|
|
|