Miscellaneous action | | | 9/22/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 7/29/2011 | 8/1/2011 | 8/1/2011 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Miscellaneous action | | | 8/1/2011 | | DONE |
|
|
|
Received As Built drawings.
|
INSP-Sprinkler Rough-in | 7/22/2011 | 7/25/2011 | 7/25/2011 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping can be covered. The branchline tie-ins are not completed but will be verified from the mechanical mezzanine at the final inspection. Also sprinkler coverage will be required under the duct work on the mechanical mezzanine as discussed.
|
Issue and Print Permit | | | 4/28/2011 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 4/19/2011 | | 4/26/2011 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/26/2011 | | 4/26/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 4/26/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/26/2011 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/26/2011 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 4/26/2011 | | 4/26/2011 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 4/26/2011 | | DONE |
Barbara Stitt
|
|
|
CalledDon and told him that permit id ready & fees due on 4-26-11 @ 9:05am
|
Plan resubmittals received | | | 4/21/2011 | | DONE |
|
|
|
receiced 3 sets of plans/applications sent to fire ///dld
|
Sprinkler Plan Check | 4/20/2011 | | 4/20/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 4/20/2011 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 4/20/2011 | | DONE |
|
|
|
Emailed review to contractor
|
Telephone call | | | 4/20/2011 | | DONE |
|
|
|
t/c w don - permit denied - needs to be picked up and resubmitted
|
Application received | | | 4/19/2011 | | |
|
|
|
|