Miscellaneous action | | | 6/8/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 5/25/2011 | 5/26/2011 | 5/26/2011 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 5/24/2011 | 5/25/2011 | 5/25/2011 | A | PASS |
Troy Cobbley
|
|
|
Hydro test of the wet and dry system passed.
|
INSP-Sprinkler Rough-in/Hydro | 5/23/2011 | 5/24/2011 | 5/24/2011 | A | FAIL |
Troy Cobbley
|
|
|
Arrived on site but Don and I found visual leaks that he was going to repair. No hydro testing was able to be performed. Rescheduled for tomorrow.
|
INSP-Sprinkler Rough-in | 5/12/2011 | 5/13/2011 | 5/13/2011 | A | PASS |
Troy Cobbley
|
|
|
Need to provide sprinkler protection under the overhead door and provide hydro test.
|
INSP-Sprinkler Rough-in | 5/5/2011 | 5/6/2011 | 5/6/2011 | P | PASS |
Troy Cobbley
|
|
|
The breezeway sprinkler piping can be covered. The dry pendant heads are to be installed later.
|
INSP-Sprinkler Rough-in | 4/28/2011 | 4/28/2011 | 4/28/2011 | P | PASS |
Troy Cobbley
|
|
|
The hard lid ceilings are ok to cover.
|
Plan assigned to (Tim) | 4/22/2011 | | 4/27/2011 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 4/27/2011 | | DONE |
Christina Prado
|
|
|
Received three copies of application; checklist; response letter; Reliable calcs and plan FP1 of 1. Routed to Tim Frost for review
|
Sprinkler Plan Check | 4/27/2011 | | 4/27/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 4/27/2011 | | 4/27/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 4/27/2011 | | DONE |
|
|
|
t/c w jeff anderson - permit ready and fees given
|
Permit Ready to Issue | | | 4/27/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/27/2011 | | DONE |
|
|
|
|
Telephone call | | | 4/22/2011 | | DONE |
|
|
|
t/c w jeff anderson - permit denied - needs to be picked up and resubmitted
|
Miscellaneous action | | | 4/22/2011 | | DONE |
|
|
|
Emailed review to contractor
|
Pending Assignment by SAM | 4/20/2011 | | 4/22/2011 | | DONE |
Patricia Smith
|
|
|
|
Sprinkler Plan Check | 4/22/2011 | | 4/22/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 4/22/2011 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 4/20/2011 | | |
|
|
|
|